EuroAsia Interconnector Submarine Power Cable Installation Study

  Nicosia Cyprus — EuroAsia Interconnector Limited
Published July 20, 2016 — Deadline September 9, 2016 (2 years ago)
|
Notice type
Contract notice

The EuroAsia Interconnector project links the electrical systems of Israel, Cyprus and continental Greece (via Crete) through 500 KV sub-marine DC cables and HVDC onshore stations in each country/location and have a total capacity of 2 000 MW. The project creates an energy bridge between the two continents with a total length of the interconnector of 1 520 km, and creates a reliable alternative corridor for transferring electricity to Europe and allow for reverse transmission of electricity.

Stage 1 of the EuroAsia Interconnector consist of a 500 kV submarine cable with a total capacity of 1 000 MW and 8 HVDC onshore stations.

The project promoter of the EuroAsia Interconnector is EuroAsia Interconnector Limited, a subsidiary of Cyprus-based Quantum Energy Limited and with the participation of Greek Public Power Corporation (PPC) S.A. The interconnector project has been included in the list of Projects of Common Interest (PCI) of the European Union, as a cluster PCI consisting of the following PCIs:

· PCI 3.10.1 — Interconnection between Hadera (IL) and Kofinou (CY)

· PCI 3.10.2 — Interconnection between Kofinou (CY) and Korakia, Crete (EL)

· PCI 3.10.3 — Internal line between Korakia, Crete(EL) and Attica region (EL) Pachi

The project is at its final design phase prior to the commencement of construction works.

The general Scope of Work of the proposal is to provide a cable installation study for the EuroAsia Interconnector Cable. This includes the review of available data, route analysis, cable installation, cable protection and landfall construction.

The Scope of Work of the study consists of the parts shown below and considers the complete cable installation including the construction of the landfalls. For each of these parts, an overview is shown below along with a brief description.

1. Study Preparation, Project Management & Reporting: Basic Framework for the study, study management, meeting, documentation.

2. Risk Assessment / HAZID: Identify the acceptable risk level and necessary protection level to achieve it. Identification of the hazards that generate risk.

3. Review Data: Review of completeness and quality of the data, including cable specifications, cable route, metocean and geotechnical data, environmental requirements

4. Engineering Basis Study: Summary of all technical data to be used in the remainder of the study, with assumptions where necessary

5. Free Span Analysis: The analysis will determine the allowable free span for the cables.

6. Route Optimisation: Select most appropriate and cost effective route; prepare alignment sheets

7. Cable Length Assessment: Assessment of the estimated required cable length along the whole route

8. Cable Lay Analysis: Static and dynamic installation analysis along the whole route.

9. Repair Options: Options for making future repairs to the cable will be analyzed.

10. Pre-lay Seabed Preparation: Seabed interventions required before the cable can be installed.

11. Workability analysis: Workability analysis, including working windows required, for a set of representative vessels.

12. Protection Design: Protection philosophy, analysis of accidental loads, design of protection.

13. Landfall Site Assessment, Local Content & Site Access: Site Visit & Assessment and Investigation of locally available resources.

14. Landfall Installation Method Statement: Selection pf most suitable method of landfall construction, storyboard, required materials and landfall specific equipment.

15. Equipment Specification: Specification of the required equipment, both vessels auxiliary equipment.

16. Project execution Plan & Method Statement: High level description of required actions, methods and procedures

17. Installation Schedule: Provisional planning of project execution.

18. Budget Estimate: High level cost estimate for the actual installation of the cable and landfalls.


Full tender details available only for Oppex usersSign in

Fact Sheet


Cyprus-Nicosia: Consultative engineering and construction services

2016/S 138-251020

Contract notice – utilities

Services

Directive 2004/17/EC

Section I: Contracting entity

I.1)Name, addresses and contact point(s)

EuroAsia Interconnector Limited
Quantum House: 25 Philippou Str., Agios Dometios
Contact point(s): EuroAsia Interconnector Limited
For the attention of: Leonidas Leonida
2363 Nicosia
Cyprus
Telephone: +357 22792200
E-mail: procurement@euroasia-interconnector.com
Fax: +357 22776799

Internet address(es):

General address of the contracting entity: http://www.euroasia-interconnector.com/

Electronic access to information: http://www.euroasia-interconnector.com/News-EuroAsia_Interconnector_Submarine_Power_Cable_Installation_Study,1056?Period=

Further information can be obtained from: The above mentioned contact point(s)

Specifications and additional documents (including documents for a dynamic purchasing system) can be obtained from: The above mentioned contact point(s)

Tenders or requests to participate must be sent to: The above mentioned contact point(s)

I.2)Main activity
Electricity
I.3)Contract award on behalf of other contracting entities
The contracting entity is purchasing on behalf of other contracting entities: no

Section II: Object of the contract

II.1)Description
II.1.1)Title attributed to the contract by the contracting entity:
EuroAsia Interconnector Submarine Power Cable Installation Study.
II.1.2)Type of contract and location of works, place of delivery or of performance
Services
Service category No 12: Architectural services; engineering services and integrated engineering services; urban planning and landscape engineering services; related scientific and technical consulting services; technical testing and analysis services
Main site or location of works, place of delivery or of performance: Eastern Mediterranean Basin between Israel, Cyprus, Crete and Attica.

NUTS code CY,GR

II.1.3)Information about a public contract, a framework agreement or a dynamic purchasing system (DPS)
II.1.4)Information on framework agreement
II.1.5)Short description of the contract or purchase(s):
The EuroAsia Interconnector project links the electrical systems of Israel, Cyprus and continental Greece (via Crete) through 500 KV sub-marine DC cables and HVDC onshore stations in each country/location and have a total capacity of 2 000 MW. The project creates an energy bridge between the two continents with a total length of the interconnector of 1 520 km, and creates a reliable alternative corridor for transferring electricity to Europe and allow for reverse transmission of electricity.
Stage 1 of the EuroAsia Interconnector consist of a 500 kV submarine cable with a total capacity of 1 000 MW and 8 HVDC onshore stations.
The project promoter of the EuroAsia Interconnector is EuroAsia Interconnector Limited, a subsidiary of Cyprus-based Quantum Energy Limited and with the participation of Greek Public Power Corporation (PPC) S.A. The interconnector project has been included in the list of Projects of Common Interest (PCI) of the European Union, as a cluster PCI consisting of the following PCIs:
· PCI 3.10.1 — Interconnection between Hadera (IL) and Kofinou (CY)
· PCI 3.10.2 — Interconnection between Kofinou (CY) and Korakia, Crete (EL)
· PCI 3.10.3 — Internal line between Korakia, Crete(EL) and Attica region (EL) Pachi
The project is at its final design phase prior to the commencement of construction works.
The general Scope of Work of the proposal is to provide a cable installation study for the EuroAsia Interconnector Cable. This includes the review of available data, route analysis, cable installation, cable protection and landfall construction.
The Scope of Work of the study consists of the parts shown below and considers the complete cable installation including the construction of the landfalls. For each of these parts, an overview is shown below along with a brief description.
1. Study Preparation, Project Management & Reporting: Basic Framework for the study, study management, meeting, documentation.
2. Risk Assessment / HAZID: Identify the acceptable risk level and necessary protection level to achieve it. Identification of the hazards that generate risk.
3. Review Data: Review of completeness and quality of the data, including cable specifications, cable route, metocean and geotechnical data, environmental requirements
4. Engineering Basis Study: Summary of all technical data to be used in the remainder of the study, with assumptions where necessary
5. Free Span Analysis: The analysis will determine the allowable free span for the cables.
6. Route Optimisation: Select most appropriate and cost effective route; prepare alignment sheets
7. Cable Length Assessment: Assessment of the estimated required cable length along the whole route
8. Cable Lay Analysis: Static and dynamic installation analysis along the whole route.
9. Repair Options: Options for making future repairs to the cable will be analyzed.
10. Pre-lay Seabed Preparation: Seabed interventions required before the cable can be installed.
11. Workability analysis: Workability analysis, including working windows required, for a set of representative vessels.
12. Protection Design: Protection philosophy, analysis of accidental loads, design of protection.
13. Landfall Site Assessment, Local Content & Site Access: Site Visit & Assessment and Investigation of locally available resources.
14. Landfall Installation Method Statement: Selection pf most suitable method of landfall construction, storyboard, required materials and landfall specific equipment.
15. Equipment Specification: Specification of the required equipment, both vessels auxiliary equipment.
16. Project execution Plan & Method Statement: High level description of required actions, methods and procedures
17. Installation Schedule: Provisional planning of project execution.
18. Budget Estimate: High level cost estimate for the actual installation of the cable and landfalls.
II.1.6)Common procurement vocabulary (CPV)

71310000, 31321300, 31321500

II.1.7)Information about Government Procurement Agreement (GPA)
II.1.8)Information about lots
II.1.9)Information about variants
Variants will be accepted: no
II.2)Quantity or scope of the contract
II.2.1)Total quantity or scope:
II.2.2)Information about options
Options: no
II.2.3)Information about renewals
This contract is subject to renewal: no
II.3)Duration of the contract or time limit for completion

Section III: Legal, economic, financial and technical information

III.1)Conditions relating to the contract
III.1.1)Deposits and guarantees required:
Submission of guarantees is not required during the pre-qualification stage. The participation guarantee required during the award stage as well as other guarantees will be defined in the invitation to tender.
III.1.2)Main financing conditions and payment arrangements and/or reference to the relevant provisions governing them:
Co-Financing from European funding such as the Connecting Europe Facility (CEF) is under consideration.
III.1.3)Legal form to be taken by the group of economic operators to whom the contract is to be awarded:
Eligible for participation in the present tender procedure are all interested Economic Operators (natural and/or legal persons governed by public or private law or consortia of legal persons).
Consortia of natural and/or legal persons may jointly participate in the Tender, under the condition that the participation proportion of each person of the consortium is clearly stated in the Request for Participation.
Consortia are not obliged to take a specific legal form in order to participate in the tender procedure. If the selected Contractor is a consortium, then such consortium shall not be obliged to take a specific legal form before the Contract is signed.
Every natural or legal person may participate in the tender procedure either individually or in one consortium only.
To implement the Contract Scope, the Candidate may use subcontractors. It is understood that in the event the Candidate intends to subcontract to third parties any share of the contract, the Candidate, in preparing his Request to Participate, has been informed whether the same subcontractor participates in any way whatsoever in another Request to Participate in the same tender procedure. Pre-selected economic operators should indicate in their tender the specific part of the contract that they intend to subcontract to third parties. This indication shall be without prejudice to the question of the principal economic operator's liability.
III.1.4)Other particular conditions:
The performance of the contract is subject to particular conditions: yes
Description of particular conditions: With regard to the implementation of the Contract Scope, Candidates are assumed to be familiar with all relevant laws and Regulations of the places of delivery of the Contract as specified in Section II.1.2, which affect, either directly or indirectly the implementation of the contract scope.
III.2)Conditions for participation
III.2.1)Personal situation of economic operators, including requirements relating to enrolment on professional or trade registers
Information and formalities necessary for evaluating if the requirements are met: To participate in the tender procedure, interested economic operators must meet the following requirements concerning their personal situation:
a. They must not have been convicted by final judgement of a Cypriot or foreign court for participation in criminal organization (as defined in Article 2(1) of Council Joint Action 98/773/JHA), corruption (as defined in Article 3 of the Council Act of 26.5.1997 and Article 2(1) of framework decision 2003/568/JHA, respectively), fraud (within the meaning of Article 1 of the 27.11.1995 Convention relating to the protection of the financial interests of the European Communities) or money laundering and terrorist financing (as defined in Article 1 of Directive 2005/60/EC of the European Parliament and of the Council).
b. They must not be bankrupt or in the process of being wound up, have their affairs administered by the court, have entered into an arrangement with creditors, have suspended business activities or be in any analogous situation arising from a similar procedure under national laws and regulations.
c. They must not be the subject of proceedings for a declaration of bankruptcy, for an order for compulsory winding up or administration by the court or of an arrangement with creditors or of any other similar proceedings under national laws and regulations.
d. They must not have been convicted by a judgement which has the force of res judicata of any offence concerning their professional conduct.
e. They must not have been found guilty of grave professional misconduct proven by any means which the Contracting Authority can demonstrate.
f. They must have fulfilled their obligations relating to the payment of social security contributions and their obligations relating to the payment of taxes and duties as at the closing date for the submission of Requests to Participate, in accordance with the legal provisions of the Republic of Cyprus or with those of the country where they are established.
g. They must not have been found guilty of serious misrepresentation in supplying the information required above and have not failed to supply such information.
It is understood that if the interested economic operator is a consortium of persons, the above requirements must be met by all consortium members.
The same requirements must be met by the entities whose capacities the Candidate is invoking.
For certifying the eligibility for participation in accordance with the above criteria, interested Economic Operators must submit the following:
a. If the Candidate is a legal person, official proof of its establishment.
b. If the Candidate is a consortium of natural and/or legal persons, the above supporting documents should be submitted for each legal person participating in the consortium. A Cooperation Agreement, signed by all participants in the consortium, should also be submitted, stating.
i. The intention of each participant to participate in the consortium,
ii. The expected participation rate and the role of each member of the consortium,
iii. The consortium member to act as the leader of the consortium, and
iv. The person appointed as Representative of the consortium.
c. The Solemn Declaration Certifying the Candidate's Personal Situation, a template (Form 2) for which is contained in the Invitation to Participate.
d. Certification regarding the protection of employees, in the format of the template contained in the Invitation to Participate (Form 5).

Interested economic operators may obtain information on the obligations deriving from the provisions of the legislation on the protection of the employees and on working conditions currently in force in the Republic of Cyprus and applicable to the place of execution of the Contract Scope, from the Website of the Department of Labour Inspection (www.mlsi.gov.cy/dli).

The full text of the invitation to participate and relevant forms are available at the URL provided in section I.1.
III.2.2)Economic and financial ability
Information and formalities necessary for evaluating if the requirements are met: To participate in the tender procedure, interested economic operators must meet the following requirements concerning their economic and financial standing:
a. Their average annual turnover for the last 3 (three) financial years must be at least equal to EUR 5 000 000 (Five Million Euro).
b. Their average annual operating results for the last 3 (three) years must be positive.
An interested economic operator may rely on the capacities of other entities, regardless of the legal nature of the links it has with them, in order to fulfil the above requirements. In such a case, it must be able to prove to the Contracting Entity that it shall have at its disposal the resources necessary.
It is understood that if the interested economic operator is a consortium of persons, it is sufficient for the above requirements to be met cumulatively by the consortium members.
For certifying the Economic and Financial Standing of the Candidate, the Candidate must submit the relevant Table, a template for which is contained in the Invitation to Participate (Form 3), duly completed and accompanied by copies or extracts of the audited financial statements for the last 3 (three) financial years, where the Candidate is obliged to publish audited financial statements (where the publication of audited financial statements is required under the company laws of the country where the Candidate is established) or a Statement of the respective required financial data where the latter is not obliged to publish audited financial statements.
The full text of the invitation to participate and relevant forms are available at the URL provided in section I.1.
III.2.3)Technical capacity
Information and formalities necessary for evaluating if the requirements are met: To participate in the tender procedure, interested economic operators must meet the following requirements concerning their technical and professional ability:
a. They must possess, and be able to document adequately, know-how and experience in the implementation of contracts similar to the contract being put out to tender and, more specifically, they must possess experience in submarine power cable installation studies;
b. They must have completed successfully at least 3 contracts with the object described in point (a) above, with a participation rate of more than 50 % during the period 2007 — 2016. The term ‘completed’ shall mean that implementation of the respective contract is at least 60 % complete, in terms of the amount disbursed, with respect to the total value of the project, as of the date of submission of the Request to Participate.
It is understood that if the interested economic operator is a consortium of persons, it is enough for the above requirements to be met cumulatively by the consortium members.
Interested economic operators should be certified in accordance with the CYS EN ISO 9000 series of Cyprus standards, by a recognised Institute or Organisation, for the provision of services similar to those put out to tender, or hold some other equivalent certification issued by Organisations having their registered office in Member States of the European Union, or other proof of the existence of equivalent quality assurance measures for the services that they provide. It is understood that if the interested economic operator is a consortium of persons, the above requirements must be met by all consortium members.
An interested economic operator may rely on the capacities of other entities, regardless of the legal nature of the links it has with them, in order to fulfil the above requirements. In such a case, it must be able to prove to the Contracting Entity that it shall have at its disposal the resources necessary.
The number of suitable Candidates to be invited to tender is set to a minimum of 3 (provided that there are sufficient suitable Candidates) and to a maximum of 5.
If, during the verification procedure, it is found that the Candidates whose Requests to Participate meet all participation requirements above are more than the number of Candidates to be invited to tender as specified, the Opening/Evaluation Committee shall conduct a comparative evaluation in order to select the 5 best Candidates, whom it shall invite to tender at the next stage of the tender procedure.
The comparative evaluation of Candidates shall be conducted using the following criterion:
a. Total number of each Candidate's contracts meeting the above requirements and involve submarine power cable installation studies that have been conducted. In the case of Candidates obtaining the same mark after being evaluated using the above criterion, these shall be ranked using the following criterion:
b. Comparative criterion 2: Total budget of each Candidate's contracts meeting the above requirements.
After evaluating the Requests to Participate of the Candidates meeting all participation requirements using the first criterion, the Opening/Evaluation Committee shall rank the Candidates in decreasing order of the degree of fulfilment of this criterion, and shall draw up relevant Minutes. From this ranking, the top 5 Candidates shall be invited to tender at the next stage of the tender procedure.
For certifying the technical and professional ability of the Candidate, the following must be submitted:
i. A list of contracts, showing that the participation requirements specified above are met, which should be in the format of the template contained in Invitation to Participate (Form 4);
ii. Information documenting the successful implementation of the contracts of the above list, as follows:
— If the Employer is a Public Entity, a relevant certificate issued by the competent Public Authority and proof of final payment for the full settlement of the contract amount;
— If the Employer is a private entity, a certificate from that private entity or, failing this, a simple declaration by the Candidate in which the data of the contact person at the entity where the contract was executed must be given and proof of final payment for the full settlement of the contract amount.
iii. A certificate issued by an independent organisation, attesting the compliance of the Candidate with a quality assurance standard based on the CYS EN ISO 9000 series of Cyprus standards, or other equivalent certifications issued by bodies established in other Member States of the European Union, or other evidence of equivalent quality assurance measures.
If the Candidate relies on the capacities of other entities, submission of the following supporting documents are required:
i. Declarations by these entities, whereby they shall guarantee to the Contracting Authority that, should the Candidate be appointed Contractor, they shall place at its disposal the necessary resources as appropriate (Form 6 — Provided in the Invitation to Participate);
ii. The declaration of sub-paragraph (c) of Section III.2.1.
It is understood that in such a case, the supporting documents of regarding the economic, financial, and technical capacity should also include the documents concerning these entities, depending on the resources made available.
The full text of the invitation to participate and relevant forms are available at the url provided in section I.1.
III.2.4)Information about reserved contracts
III.3)Conditions specific to services contracts
III.3.1)Information about a particular profession
III.3.2)Staff responsible for the execution of the service

Section IV: Procedure

IV.1)Type of procedure
IV.1.1)Type of procedure
Negotiated
Some candidates have already been selected (if appropriate under certain types of negotiated procedures): no
IV.2)Award criteria
IV.2.1)Award criteria
The most economically advantageous tender in terms of the criteria stated in the specifications or in the invitation to tender or to negotiate
IV.2.2)Information about electronic auction
An electronic auction will be used: no
IV.3)Administrative information
IV.3.1)File reference number attributed by the contracting entity:
2150/1/2016
IV.3.2)Previous publication(s) concerning the same contract
no
IV.3.3)Conditions for obtaining specifications and additional documents (except for a DPS)
IV.3.4)Time limit for receipt of tenders or requests to participate
9.9.2016 - 12:00
IV.3.5)Language(s) in which tenders or requests to participate may be drawn up
English.
IV.3.6)Minimum time frame during which the tenderer must maintain the tender
IV.3.7)Conditions for opening of tenders

Section VI: Complementary information

VI.1)Information about recurrence
This is a recurrent procurement: no
VI.2)Information about European Union funds
The contract is related to a project and/or programme financed by European Union funds: yes
Reference to project(s) and/or programme(s): The EuroAsia Interconnector project has been included in the list of Projects of Common Interest (PCI) of the European Community, as a cluster PCI 3.10 consisting of the following PCIs:
— PCI 3.10.1— Interconnection between Hadera(IL) and Kofinou(CY);
— PCI 3.10.2 — Interconnection between Kofinou(CY) and Korakia, Crete (EL);
— PCI 3.10.3 — Internal line between Korakia, Crete(EL) and Attica region (EL).
The project promoter of the EuroAsia Interconnector is EuroAsia Interconnector Ltd., a subsidiary of Cyprus-based Quantum Energy Ltd and with the participation of Greek Public Power Corporation S.A. (PPC)
Expected timing for further Notices is placed in the following 12 months.
VI.3)Additional information:

Detailed instructions on the format and submission of requests, required forms that must be completed as well as all conditions applicable to the present notice are provided in the relevant invitation to participate available at http://www.euroasia-interconnector.com/News-EuroAsia_Interconnector_Submarine_Power_Cable_Installation_Study,1056?Period= All interested economic operators must download and consult the invitation to participate before preparing their requests to participate. The invitation to participate is available in English

The Tender process will take place in 2 stages:
a. Pre-selection stage: Invitation to all interested Economic Operators to submit Requests to Participate, so that qualified Candidates may be selected to submit a Tender. The evaluation and selection of qualified economic operators will be performed according to the process and criteria described in this Invitation.
b. Award stage: Invitation of qualified candidates to submit a Tender and take place in negotiations. Details of the Tender evaluation and negotiation processes to be provided in the Request for Proposal that will be sent to qualified economic operators along with the invitation to submit a tender.
Interested Economic Operators may submit their inquiries/comments/suggestions regarding the Tender processing writing via fax, e-mail or letter at the contact information provided in this notice, by 26.8.2016 at 12:00. The Contracting Authority shall provide written answers to any questions that will have been submitted in due time, at the above URL, by 2.9.2016. It is noted that under no circumstance may Economic Operators rely or invoke any verbal information provided by personnel of the Contracting Authority.
Every Economic Operator being interested in the conclusion of a contract with EuroAsia Interconnector Ltd shall be entitled to contest, by lodging an appeal, any enforceable act of the Contracting Authority related to the selection procedure which he considers as affecting his interests in an unlawful manner
This appeal is exercised in accordance with the requirements of the applicable legislation for extending legal protection at the stage which precedes the conclusion of the contract.
The time limits for lodging the appeal and for subsequent recourse, if any, to provisional remedies shall entail only the restraints imposed by the law.
Every appeal, in accordance with the aforementioned, shall be against EuroAsia Interconnector Ltd and examined by a responsible Appeals Committee, who/which shall issue a justified decision thereon within the time limit provided for by the standing legislation in force from time to time that will be provided in writing to the party lodging the appeal. If such time limit elapses inactive, it shall be inferred that the appeal has been dismissed.
The Tender procedure shall be conducted in accordance with Directive 2004/17/EC of the European Parliament and of the Council as applicable.
By submitting their Requests to Participate, Candidates are assumed to be familiar with all relevant laws and Regulations of the Republic of Cyprus which affect, either directly or indirectly, the tender procedure. With regard to the implementation of the Contract Scope, Candidates are assumed to be familiar with all relevant laws and Regulations of the places of delivery of the Contract as specified in Section II.1.2, which affect, either directly or indirectly the implementation of the contract scope.
Contracting Authority will consider as acceptable those Requests to Participate which comply with all terms and conditions of this invitation and may also accept any Request to Participate with insignificant deviations based on its judgement and discretion. Insignificant deviations are considered to be differences that do not affect the scope of the contract's object or the quality of its execution, do not substantially restrict the rights of the Contracting Authority or the obligations of the Contractor and do not affect the principal of equal treatment of tenderers.
Any attempt by or on behalf of a Candidate to influence in any way whatsoever the judgement of the Contracting Authority or of the Opening/Evaluation Committee in the discharge of their duties in connection with the tender procedure or result, shall result in the rejection of its Request to Participate.
Candidates who have obtained or taken in their possession, without legal authority and at their own initiative, information or documents of a secret nature in connection to the tender procedure, shall be excluded from participation.
VI.4)Procedures for appeal
VI.4.1)Body responsible for appeal procedures
VI.4.2)Lodging of appeals
VI.4.3)Service from which information about the lodging of appeals may be obtained
VI.5)Date of dispatch of this notice:
16.7.2016

Oppex helps organizations with a professional approach to public sector sales, to either grow their business locally or find new opportunities abroad. We are the largest source of public procurement data in Europe. We process and translate public tenders from over 1.000 local, national and international procurement portals and have acquired over 8 million tenders in our database.