Engineering design services

Urząd Miasta i Gminy Skawina | Published July 30, 2015
Winner
POLINVEST Sp. z o.o. – Lider Konsorcjum
cpvs
71320000

The contract is for the execution of development studialno - concept in the field of investment areas (economic zone) in Skawina including the performance of studies: 1) The concept of functional - usable development of economic zones in Skawina together with the estimated costs and examining the impact on the environment, 2) functional - utility program. feasibility study and environmental impact assessment for the project "Development of Economic Activity Zone - Phase III", 3) The functional - utility, feasibility study and environmental impact assessment for the project development Economic Area "Huta".

Engineering design services

Urząd Miasta i Gminy Skawina | Published May 16, 2015  -  Deadline June 23, 2015
cpvs
71320000

The contract is for the execution of development studialno - concept in the field of investment areas (economic zone) in Skawina including the performance of studies: 1) The concept of functional - usable development of economic zones in Skawina together with the estimated costs and examining the impact on the environment, 2) The functional - utility, feasibility study and environmental impact assessment for the project "Development of Economic Activity Zone - Phase III", 3) The functional - utility, feasibility study and environmental impact assessment for the project development Economic Area "HUTA".

Engineering design services

Urząd Miasta i Gminy Skawina | Published August 15, 2015  -  Deadline September 22, 2015
cpvs
71320000

The contract is for the execution of the development study and concept for the area of ​​economic activity Mnikow / Cholerzyn / Morawica, including: 1) The concept of functional - usable development of economic activity zones Mnikow / Cholerzyn / Morawica (MChM) together with the estimated costs and examining the impact on the environment, 2 ) Program functional - utility, feasibility study and environmental impact assessment for the economic activity zone Mnikow / Cholerzyn / Morawica (MChM) - Stage I Cholerzyn, 3) Program functional - utility, feasibility study and environmental impact assessment for the zone economic activity Mników / Cholerzyn / Morawica (MChM) - Phase II Morawica, 4) Program functional - utility, feasibility study and environmental impact assessment for the economic activity zone Mnikow / Cholerzyn / Morawica (MChM) - Phase III Mników.

Construction work for water and sewage pipelines

Zakład Wodociągów i Kanalizacji Sp. z o.o. | Published November 16, 2017  -  Deadline January 3, 2018
cpvs
45231300, 45000000, 45232400, 45232151, 45232152, 45231100, 45232411, 45111300, 45233140, 45233200, 45111291

Contract No 4 (Contract 4.1) - Construction of a sewerage network in the commune of Skawina Jaśkowice - Zelczyna - part I. The task of the contract is to perform construction works on contractual conditions for construction work for engineering and construction projects designed by the Contracting Authority. No. 5 (Contract 5.1) - Construction of a sewage network in the municipality of Skawina Grabie - Krzęcin - part I ".

The scope of the contract covers the realization of the project. "Water and sewage management in the Skawina Commune" - stage II and is part of the five tasks (contracts) of the water and sewage network of this Project, and under this procedure is execution of contracts ie:

"Task No. 4 (Contract 4.1) - Construction of a sewage network in the commune of Skawina Jaśkowice - Zelczyna - part I.

Task No. 5 (Contract 5.1) - Construction of a sewage network in the municipality of Skawina Grabie - Krzęcin - part I ".

The above mentioned tasks were covered by the application for EU funds to NFOŚiGW under the perspective of the Operational Program Infrastructure and Environment 2014-2020 and are part of the project "Water and sewage management in the Skawina Commune - stage II".

Parameters, scope and order location:

1. Location of investment - Zelczyna and Krzęcin

2.The value of the investment cost estimate of 6.811.129,07 PLN net

Gravity tanks with a diameter of 150-1000 mm with a length of 7,386.9 m

4. Discharge pipelines with a diameter of 40-280 mm with a length of 931.0 m

5. Network pumps - pcs. 2

6. District roads: reconstruction of asphalt roads - binding layer 2406.7 m², wear layer 6687.0 m², roadside 1671.8 m2,

7.Generous roads: reconstruction of asphalt roads - binding layer 5897.1 m², wear layer 5897.1 m², reconstruction of road junction 886.2 m2.

Environmental improvement works

CEZ Skawina S.A. | Published January 11, 2017  -  Deadline February 2, 2017
cpvs
45262640, 45220000, 45210000

The contract is for installation of flue gas denitrification of OP-210M (K8 - K11) and 1 OP-230 (K6) in CEZ Skawina SA using catalytic SCR "Low Dust" or "Tail End" in the formula "turnkey" assuming while working only 4 boilers.

Purchaser expects perform installation guaranteeing the achievement of the level of NOx emissions of less than 150 [mg / Nm3] or other required after the publication of the final, the current requirements of BREF / BAT for LCP.

Environmental improvement works

CEZ Skawina S.A. | Published October 24, 2017
Winner
Sąd Arbitrażowy przy Krajowej Izbie Gospodarczej
cpvs
45262640, 45220000, 45210000

The OP-210M (K8 - K11) and one OP-230 (K6) boiler in the CEZ Skawina SA catalytic converter "Low Dust" or "Tail End" in the "turnkey" formula under the assumption Simultaneous operation of only 4 boilers.

The contractor expects to install a NOx Exhaust Gas Concentration below 150 [mg / Nm3] or another required after the final BREF / BAT for LCP.

The OP-210M (K8 - K11) and one OP-230 (K6) boiler in the CEZ Skawina SA catalytic converter "Low Dust" or "Tail End" in the "turnkey" formula under the assumption Simultaneous operation of only 4 boilers.

The contractor expects to install a NOx Exhaust Gas Concentration below 150 [mg / Nm3] or another required after the final BREF / BAT for LCP.

  • 1