Call +44 800 9755 164

Public tenders for power-transformer

Find all Energy tenders in the world.
Finding business opportunities has never been easier.

Results for energy. Make a new search!
Energypower transformer

Acquisition of fuse and power transformer.

MINISTÉRIO DAS MINAS E ENERGIA | Published April 19, 2017  -  Deadline May 3, 2017
cpvs

Object: Electronic Auction - Acquisition of fuse and power transformer.

Purchasing power transformer with delivery to the city settlement work settlement Chegdomyn

АДМИНИСТРАЦИЯ ГОРОДСКОГО ПОСЕЛЕНИЯ #034;РАБОЧИЙ ПОСЕЛОК ЧЕГДОМЫН#034; ВЕРХНЕБУРЕИНСКОГО МУНИЦИПАЛЬНОГО РАЙОНА ХАБАРОВСКОГО КРАЯ | Published October 14, 2016  -  Deadline October 20, 2024
cpvs

Power transformer 27.11.42.000 PCs of 1.00 369 369 029,00 029,00 total: 369 029,00

Maintenance kV package transformer substations with the current kV power transformer repairs

МУНИЦИПАЛЬНОЕ БЮДЖЕТНОЕ УЧРЕЖДЕНИЕ ЗДРАВООХРАНЕНИЯ #034;КРАСНОАРМЕЙСКАЯ ЦЕНТРАЛЬНАЯ РАЙОННАЯ БОЛЬНИЦА#034; | Published October 17, 2016  -  Deadline October 20, 2024
cpvs

Maintenance of 10 / 0.4 kV and current repairs of power transformer 400 kV 33.14.11.000 cond. U 1.00 89 930.55 89 930.55 Total 89 930.55

(ESO-2017-560) 11-transformer reconstruction of the transit modular transformer, power transformer replacement, Kaunas distr., Works

UAB Verslo aptarnavimo centras | Published April 10, 2017
cpvs
45311000

(ESO-2017-560) 11-transformer reconstruction of the transit modular transformer, power transformer replacement, Kaunas distr., Works

(Nos. ESO-2017-508) 11-transformer replacement in MTT power transformer replacement, Kaunas r., Works

UAB Verslo aptarnavimo centras | Published April 5, 2017
cpvs
45311000

(Nos. ESO-2017-508) 11-transformer replacement in MTT power transformer replacement, Kaunas r., Works

Acquisition and installation of power transformer

MINISTÉRIO DA AGRICULTURA, PECUÁRIA E ABASTECIMENTO | Published April 20, 2017  -  Deadline May 4, 2017
cpvs

Object: Electronic Auction - Acquisition and installation of energy transformer

Revitalization of the first power transformer 20 MVA

HEP-Operator distribucijskog sustava d.o.o. | Published March 28, 2017
cpvs
50532200

power transformers

ETD TRANSFORMÁTORY a.s. | Published January 9, 2017  -  Deadline September 2, 2017
cpvs
31170000

Delivery of power transformers HV / MV.

Delivery of power oil transformer

АДМИНИСТРАЦИЯ СОЛНЕЧНОГО МУНИЦИПАЛЬНОГО РАЙОНА ХАБАРОВСКОГО КРАЯ | Published September 22, 2016  -  Deadline September 20, 2030
cpvs

The power transformer in the case of TMG-630/10/0,4 kV 27.11.41.000 PCs 1,00 500 000,00 500 000,00 total: 500 000,00

Tampere Electricity Network Ltd's päämuuntajahankinta 2017

Tampereen Sähköverkko Oy | Published March 16, 2017  -  Deadline May 2, 2017
cpvs
31171000

According to Hankintaohjeman. The acquisition includes Lamminpään 2 substation main transformer BT50. 1 pcs 117 ± 9x1,67% / 21 kV, 32 MVA, ONAN (ONAF 125%, or 40 MVA) power transformer 110 kV Over-voltage electric station Lamminpään installed in place and tested, as well as the transformer needed for the use of accessories. The acquisition includes Lamminpään 2 substation main transformer BT50. 1 pcs 117 ± 9x1,67% / 21 kV, 32 MVA, ONAN (ONAF 125%, or 40 MVA) power transformer 110 kV Over-voltage electric station Lamminpään installed in place and tested, as well as the transformer needed for the use of accessories. Variants will be accepted (alternative tenders) does not list the selection criteria and their short-list of selection criteria and their short-list and brief Hankintaohjeman by.

Liquid dielectric transformers

Tampereen Sähköverkko Oy | Published March 17, 2017  -  Deadline May 2, 2017
cpvs
31171000

The acquisition includes Lamminpään 2 substation main transformer BT50.

1 pcs 117 ± 9x1,67% / 21 kV, 32 MVA, ONAN (ONAF 125%, or 40 MVA) power transformer 110 kV Over-voltage electric station Lamminpään installed in place and tested, as well as the transformer needed for the use of accessories.

The U.S. Army Corps of Engineers (USACE) Transatlantic Afghanistan District (TAA) has a requirement for construction of facilities necessary to deliver electricity to the 1/111th Corps Garrison at Darulaman, Camp Commando Garrison, and MFDU Garrison

Department of the Army, U.S. Army Corps of Engineers | Published April 18, 2017  -  Deadline May 3, 2017
cpvs

The U.S. Army Corps of Engineers (USACE) Transatlantic Afghanistan District (TAA) has a requirement for construction of facilities necessary to deliver electricity to the 1/111th Corps Garrison at Darulaman, Camp Commando Garrison, and MFDU Garrison. The 1/111th Corps Garrison at Darulaman, Camp Commando Garrison, and MFNDU Garrison electrical connections will be offered as a single contract. An expansion of the Brishnakot substation is required to distribute one 20 kV circuits to 1/111th Corps Garrison at Darulaman and the Camp Commando Garrison in Kabul Province. To provide reliable power to MFNDU, an expansion of the North-West substation is necessary to distribute one 20 kV circuit. The substation expansions shall include the design of a new 20 kV yard with indoor switchgear, connection to one 110 kV/20-15 kV power transformer rated no less than 25 MVA, one 20 kV line bay capable of expansion to 34 MVA, and line dead-end structures for connection to four 20 kV distribution system lines. The project will include the electrical distribution inside the ANA facilities as well.  The project will include the material, labor, and all other construction components of the project as shown in the conceptual plans and technical specifications. Work will also include civil site work, to include grading, leveling and compaction for facility/tower construction.  Additional work includes demining the transmission line routes and substation locations, and project security.  Any and all deficient work will be repaired or replaced. The Contractor shall provide a complete and fully functioning power system.  These electrical power distribution system and substation shall be designed and constructed in accordance with current electrical and building codes, safety, and security standards, and applicable to local standards. This project will be awarded based on the CLINs in the bid schedule and will be awarded to a single offeror.

SUPPLY OF POWER TRANSFORMERS SWITCHING-5,5KV 22kV / 400V, 630KVA and 400KVA

Office Nationale de l'Electricité et de l'Eau Potable - Branche Electricité | Published February 20, 2017  -  Deadline April 26, 2017
cpvs

21st PURCHASE, DELIVERY AND INSTALLATION OF POWER TRANSFORMERS 110 10.5 (21) kV, 40 MVA 110 kV High 10

Hrvatska elektroprivreda d.d. | Published December 27, 2016  -  Deadline August 2, 2017
cpvs
31170000

Open auction in electronic form for the right of concluding the state contract for the supply of a complete two-transformer substations with power transformers

ГОСУДАРСТВЕННОЕ КАЗЕННОЕ УЧРЕЖДЕНИЕ РЕСПУБЛИКИ ДАГЕСТАН #034;ДИРЕКЦИЯ СТРОЯЩИХСЯ ОБЪЕКТОВ #034;НОВОСТРОЙ#034; | Published October 17, 2016  -  Deadline October 20, 2024
cpvs

Delivery of the complete two-transformer substations with power transformers 27.11.43.000 units of 1.00 935 935 550,00 550,00 total: 935 550,00

Replacement of Runway 12 MALSR System at Huron Regional Airport, Huron, South Dakota

Department of Transportation, Federal Aviation Administration (FAA) | Published April 17, 2017  -  Deadline May 2, 2017
cpvs

This project is for the replacement of Runway 12 Medium-Intensity Approach Lighting System with Runway Alignment Indicator Lights (MALSR) System at Huron Regional Airport in Huron, South Dakota. The contractor shall provide all labor, supervision, materials, and equipment to perform the project in accordance with the contract clauses, drawings, and specifications. The project work includes, but not limited to, the following: 1. Contract a registered land surveyor (RLS) to layout and stake MALSR shelter location, light bars and power distribution rack locations and lamp elevations. 2. Completely remove all reinforced concrete foundations pier, anchor bolts, and maintenance stands. Remove all existing underground cable if the new cables are installed in the same trench as the old one, or otherwise abandon cables 2’ minimum below grade. Remove all light bars on EMT conduits, power distribution panel, and MALSR control rack. 3. Contractor shall furnish all items not shown on the project’s official Government-Furnished Materials (GFM) list. 4. Construct concrete pads and screw-anchor foundations for all MALSR LIR pole stations, MALSR power distribution rack, EMT support MALS light stations and equipment shelter. No new foundation is needed for the existing threshold bar light station because it is structurally sound and is fairly new due to a recent replacement. 5. Set Government furnished pre-fab shelter on concrete foundation. Install lightning protection and counterpoise around shelter. Connect shelter power panel to the existing utility power transformer. Contractor shall construct the shelter floor 18 inches above the finished grade elevation. Contractor is responsible for shipping of the pre-fab 12x12 sq. ft. MALSR shelter which is currently sitting at Aberdeen airport. The shelter is equipped with a Bard HVAC unit mounted on the exterior wall. 6. Install all new Government Furnished MALSR equipment in the new MALSR shelter. Verify MALSR will operate normally on local and remote control. The air to ground radio control receiver, RC-1T5A shall be salvaged from the old shelter and re-install to the new shelter. 7. Install 2 Quazite handholes near equipment shelter as shown on plan. Handholes for power cables and control cables shall be separate. 8. Install armored cables from new MALSR shelter to MALSR power distribution rack; and from power distribution rack to all light bars and threshold bar station. Install perimeter grounding conductor. 9. All cables shall be tested per specifications after installation in the presence of the COR and SSC technicians. A written record of the test results for all of the cables shall be delivered to the COR. 10. For flasher light stations, install control cabinets, flasher junction boxes, flasher light units and the contractor furnished L-5018 junction boxes. Install power and control cables from new Malsr shelter to the flasher stations. 11. Construct crushed rock plots around MALSR foundations and around shelter, slope away from shelter. 12. Extend gravel paved access road to gate per drawings. 13. Aim lamps and flasher heads. Label each MALSR station per drawings. 14. Demolish and dispose of the existing MALSR control station/shelter and its associated components. Cut and abandon cable in place to a depth of 24 inches below finished grade. 15. Re-grade and cleanup the site on daily basis. Dispose of debris at an approved waste site. Restore all areas disturbed by construction activity or vehicles per specifications. Place and compact topsoil to make site flush with surrounding grade. Seed per specifications. 16. Participate in Contractor’s Acceptance Inspection (CAI), and quickly address any punch list items. The performance time is 30 working days. Anticipated start date of project is August 8, 2017. The estimated price range for this procurement is between $250,000 and $500,000. INTERESTED FIRMS MUST HAVE SUCESSFULLY COMPLETED SIMILAR PROJECTS BOTH IN DOLLAR AMOUNT AND SCOPE OF WORK AT AN OPERATIONAL AIRPORT. General contractors must submit their interest in subject project on company letterhead and should include the firm's name, address, telephone number, fax number, email address, and point of contact. Please submit your request to the attention of Irene Medina, to email address: irene.medina@faa.gov If you're viewing this announcement from a source other than Federal Aviation Administration Contract Opportunities (FAACO), visit https://faaco.faa.gov/index.cfm/announcement/view/27100 to view the original announcement.

Structural shell work

Creos Luxembourg SA | Published March 17, 2017  -  Deadline April 24, 2017
cpvs
45223220, 45210000, 45213000, 45213100, 45213110, 45213150, 45213200, 45213250, 45213252, 45213260, 45223210, 45223310, 45223500

This contract relates to the work of structural work to be carried out under the project of "CSL - CREOS Luxembourg Site" including:

Site installation:

- Track Creation and site installation for areas

- Establishment and maintenance of a modular office complex in containers for construction management

- Establishment and maintenance of sanitary facilities for the yard

- Mobile fences maintenance

- Establishment and operation of a waste disposal site

Construction of bearing structure, insulation and sealing:

- The construction of a parking garage partially buried (BGF: ca. 9'200m2) in predominantly prefabricated construction

- The construction of an administrative building (BGF: ca. 15'300m2) in traditional reinforced concrete building

- Construction of a regional center (BGF: ca. 4'100m2) composite construction steelwork / concrete

Masonry work:

- Non-bearing masonry work

Works of technical installations in structural work phase

- Delivery and installation of medium voltage power transformer station 400 kVA

- Implementation of provisional electrical installations for construction with switchboards

- Delivery and implementation of grounding and connection to lightning protection elements

- Delivery and implementation of empty casing and waterproof sheaths

- Realization of a temporary heating for site

- Realization of underground sanitary pipes and storm water runs

- Delivery and installation of coalescence separators

- Delivery and installation of grease separator.

  • 1