Public tenders for construction in Beja Portugal

Find all Construction tenders in the world.
Finding business opportunities has never been easier.

Results for construction. Make a new search!

Contract for design / construction of the WWTP Alvalade.

AgdA — Águas Públicas do Alentejo, SA | Published October 25, 2014
Winner
Ambiágua — Gestão de Equipamentos de Águas, SAAvenida dos Descobrimentos, Edifício Las Vegas III, n.º 63V.N. Famalicão 4760-011 geral@ambiagua.pt +351 252313494 http://www.ambiagua.pt+351 252313496
cpvs
45232421

Construction of new wastewater treatment plant wastewater to the location of Alvalade.

Consultative engineering and construction services

AgdA — Águas Publicas do Alentejo, SA | Published October 18, 2016  -  Deadline October 25, 2016
cpvs
71310000

Supervision, quality management, safety coordination work and coordination of environmental management and archaeological monitoring of the Contract of Conception / Construction of the WWTP of Montemor-o-Novo and the Contract Intercetor System Montemor-o-Novo.

Consultative engineering and construction services

AgdA — Águas Públicas do Alentejo, SA | Published November 4, 2016  -  Deadline November 3, 2016
cpvs
71310000

Supervision, quality management, safety coordination work and coordination of environmental management and archaeological monitoring of the Contract of Conception / Construction of the WWTP of Montemor-o-Novo and the Contract Intercetor System Montemor-o-Novo.

Road construction works

EDIA — Empresa de Desenvolvimento e Infraestruturas do Alqueva, SA | Published July 28, 2015
Winner
Construções JJR & Filhos, SA
cpvs
45233120

Construction of the road network of the Five Kings irrigation block - Trinity - 2nd phase, with the following key features: - extension of the CS1 Path, with a development of 400 meters, - signaling paths and safety of CS1, CS2, CS3, CS4, CS5 and CSA.

Secondary road construction work

EDIA — Empresa de Desenvolvimento e Infraestruturas do Alqueva, SA | Published May 20, 2015
Winner
Tecnovia
cpvs
45233123

Construction of the road watering block Baleizão-Quintos network - 2nd phase, with the following key features: - CA4 way, with a development 2589 meters, - signaling and safety of CA1 ways, CA2 and CA3.

Road construction works

EDIA — Empresa de Desenvolvimento e Infraestruturas do Alqueva, SA | Published April 18, 2015  -  Deadline May 26, 2015
cpvs
45233120

Construction of Road Network of the Five Kings irrigation block - Trinity - 2nd phase, with the following main features: - extension of CS1 way, with a development of 400 meters; - Signaling and safety of CS1 paths, CS2, CS3, CS4, CS5 and CSA.

Secondary road construction work

EDIA — Empresa de Desenvolvimento e Infraestruturas do Alqueva, SA | Published January 3, 2015  -  Deadline February 9, 2015
cpvs
45233123

Construction of road network of Baleizão-Fifth of irrigation block - 2nd phase, with the following main features: - CA4 way, with a development of 2589 meters, - signaling and safety of CA1 paths, CA2 and CA3.

Construction work for water projects

EDIA — Empresa de Desenvolvimento e Infraestruturas do Alqueva, SA | Published February 10, 2015
Winner
GR4PT
cpvs
45240000

Infrastructure construction in reinforced concrete with about 21 m long, 9 m high and variable width between 8.6 and 10.35 m for the installation of two thin grids with a spacing of 10 mm bars equipped with system automatic cleaning of the type 'revolving chain screen' and two band microtamisadores with a mesh of about 0.2 mm (200 microns). The construction of this infrastructure implies the destruction, to an equal extent, the initial portion of the current pipeline and the reconstruction of emboquilhamento the pipeline structure, the new position. In addition to these new bodies solid - liquid separation bodies will be built packaging / storage of the removed solids and processing of the sieves of the washing liquid through four drying beds.

Consultative engineering and construction services

AgdA — Águas Públicas do Alentejo, SA | Published May 11, 2017
Winner
Prospectiva — Projetos, Serviços e Estudos, SA
cpvs
71310000

Supervision, quality management, coordination of safety at work and coordination of environmental management and archaeological monitoring of the Construction / Construction Project of the Montemor-o-Novo WWTP and the Intertemper System of Montemor-o-Novo.

Secondary road construction work

EDIA — Empresa de Desenvolvimento e Infraestruturas do Alqueva, SA | Published May 20, 2015
Winner
Construções JJR & Filhos, SA
cpvs
45233123

Construction of the road network of the irrigation block of St. Peter-Baleizão - 2nd phase, with the following key features: - way of Apolinárias, with a development of 11,188 meters, - way EM1032, with a development of 4838 meters, - signaling and safety of CA1A ways CA1B, CA2, CA3, CA4, CA5 and CA6, watering block of St. Peter-Baleizão.

Secondary road construction work

EDIA — Empresa de Desenvolvimento e Infraestruturas de Rega, SA | Published January 10, 2015  -  Deadline February 19, 2015
cpvs
45233123

Construction of Roads of St. Peter-Baleizão Irrigation Block - Phase 2, with the following main features: - way of Apolinárias, with a development of 11,188 meters, - way EM1032, with a development of 4838 meters, - signaling and safety of CA1A paths, CA1B, CA2, CA3, CA4, CA5 and CA6, the irrigation block of St. Peter-Baleizão.

Consultative engineering and construction services

EDIA — Empresa de Desenvolvimento e Infra-estruturas do Alqueva, SA | Published October 18, 2017  -  Deadline October 26, 2017
cpvs
71310000

The scope of this Service Delivery is the management and inspection of the Construction of the Reinforcement of the Power of the Alamos Elevation Station of Alleva Multi Purpose Enterprise, located in the municipality of Portel, Évora district.

The works to be supervised include the works:

a) Installation of two new pumping groups in the lifting station (groups 5 and 6) and the execution of the concrete wrapping of the pump and the support plate of the motors;

b) Installation of two new hydropneumatic reservoirs and respective connection conduit to the existing forced conduit and execution of concrete wrapping of the conduit and support structure of the reservoirs;

c) Installation of electrical equipment in the existing substation and control building;

In the provision of services is included; the topographic support of the works, the evaluation and monitoring of the quality control system to be implemented and the verification of the technical compilation and the final screens of the projects executed in the works.

Construction work

EDIA — Empresa de Desenvolvimento e Infra-estruturas do Alqueva, SA | Published March 29, 2017  -  Deadline June 25, 2017
cpvs
45000000

The object of the contract to carry out all the work necessary for the repowering of the pumping station of the Los Alamos Purpose Enterprise Multiple Alqueva, as defined in the design drawings and include mainly:

a) Installation of 2 new pumping units in the pumping station (groups 3 and 4) and running the pump involvement of concrete and engine support slab;

b) Installation of 2 new hydropneumatic respective reservoirs and conduct the connection of existing penstock and implementation of concrete involvement of the pipeline and the reservoir supporting structure;

c) Installation of electrical equipment in the substation and the existing control building.

9.1 The object of the contract to carry out all the work necessary for the repowering of the pumping station of the Los Alamos Purpose Enterprise Multiple Alqueva, as defined in the design drawings and include mainly:

a) Installation of 2 new pumping units in the pumping station (groups 3 and 4) and running the pump involvement of concrete and engine support slab;

b) Installation of 2 new hydropneumatic respective reservoirs and conduct the connection of existing penstock and implementation of concrete involvement of the pipeline and the reservoir supporting structure;

c) Installation of electrical equipment in the substation and the existing control building.

Road construction works

EDIA — Empresa de Desenvolvimento e Infraestruturas do Alqueva, SA | Published June 10, 2015  -  Deadline June 22, 2015
cpvs
45233120

Construção de estradas

General construction work for pipelines

AgdA — Águas Públicas do Alentejo, SA | Published March 4, 2015
Winner
Submerci Construções e Urbanizaçoes, Lda
cpvs
45231100

Execution of conduct section in HDPE DN 110 mm.

Secondary road construction work

EDIA — Empresa de Desenvolvimento e Infraestruturas de Rega, SA | Published March 4, 2015  -  Deadline March 23, 2015
cpvs
45233123

Construção de estrada secundária

Secondary road construction work

EDIA — Empresa de Desenvolvimento e Infraestruturas do Alqueva, SA | Published February 24, 2015  -  Deadline March 16, 2015
cpvs
45233123

Construção de estrada secundária

Secondary road construction work

EDIA — Empresa de Desenvolvimento e Infraestruturas de Rega, SA | Published February 24, 2015  -  Deadline February 19, 2015
cpvs
45233123

Construção de estrada secundária

Water-main refurbishment construction work

AgdA — Águas Públicas do Alentejo, SA | Published August 11, 2015
Winner
CASUR — Construções, Lda
cpvs
45232151

Implementation of R. de Santa Bárbara of Standards, pipelines and water mains distributors.

Contract for construction of section 4 of the hydraulic circuit Vale do Gaio the enterprise multiple purposes Alqueva.

EDIA — Empresa de Desenvolvimento e Infraestruturas do Alqueva, SA | Published November 13, 2014
Winner
Ramalho Rosa Cobetar
cpvs
45240000

Construction of section 4 of the hydraulic circuit Vale do Gaio, consisting of: - pipeline DN 700 mm, steel, implanted in the ditch, with a length of about 3390 m, - filtration station, equipped with 2 sized filters unit for a maximum flow rate of 3200 m3 / h, with a filtration grade of 0.2 mm, - by-pass conduit DN 600 mm steel, with a length of about 42 m, - the reservoir return channel dam of Vale do Gaio, - access terminal structure of the pipeline with a length of approximately 833 m.