Construction work

Gmina Miasta Sopotu | Published December 1, 2016  -  Deadline December 16, 2016
cpvs
45000000, 45210000, 45321000, 45450000, 71314200, 71320000

The object of the procedure is the choice of the private partner for the implemented project, which was named "Energy Complex modernization of public buildings in Sopot."

The project will be carried out on the basis of a public - private partnership within the meaning of the Act on Privatisation, assuming joint implementation projects, based on the division of tasks and risks between the public entity and the private partner. It is expected that the Contractor after the process of thermal modernization will be responsible for managing the energy economy of buildings for the remaining duration of the public-private partnership in order to achieve the effect of energy, economic and environmental projects.

The scope of the order and a detailed description of the contract will be clarified in the course of a competitive dialogue.

Construction work

Gmina Miasta Sopotu | Published November 16, 2016  -  Deadline December 16, 2016
cpvs
45000000, 45210000, 45321000, 45450000, 71314200, 71320000

The object of the procedure is the choice of the private partner for the implemented project, which was named "Energy Complex modernization of public buildings in Sopot."

It is expected that the Contractor after the process of thermal modernization will be responsible for managing the energy economy of buildings for the remaining duration of the public-private partnership in order to achieve the effect of energy, economic and environmental projects.

The scope of the order and a detailed description of the contract will be clarified in the course of a competitive dialogue.

The contract is for comprehensive thermal modernization of public buildings in the town of Sopot.

The scope of the order and a detailed description of the contract will be clarified in the course of a competitive dialogue.

The planned scope of the project includes the following buildings and works:

Kindergarten No. 1: The modernization of the lighting and the installation of an energy management system;

Kindergarten No. 4: The modernization of the lighting and the installation of an energy management system;

Kindergarten No. 8: Modernisation of lighting and the installation of an energy management system;

Kindergarten No. 12: modernization of the lighting and the installation of an energy management system;

Kindergarten No. 1 - nursery modernization of lighting and the installation of an energy management system;

Primary School No. 8: Modernisation of lighting and the installation of an energy management system;

Primary School No. 9: modernization of the lighting and the installation of an energy management system;

School No. 3: lighting retrofit and installation of an energy management system;

School No. 1 modernization and installation of lighting energy management system;

II LO - main building: the modernization of the lighting and the installation of an energy management system;

II LO - gym: lighting retrofit and installation of an energy management system;

Middle School No. 2: lighting retrofit and installation of an energy management system;

Center for Continuing Education - main building: thermo-modernization works, modernization and installation of lighting energy management system;

Independence 749): modernization of lighting and installation of an energy management system;

Music School: a lighting retrofit and installation of an energy management system;

School No. 5: modernization of the lighting and the installation of an energy management system;

Primary School No. 1 modernization and installation of lighting energy management system;

Kindergarten No. 10: modernization of the lighting and the installation of an energy management system;

Sopot Focus Plastic modernization of lighting and the installation of an energy management system;

Kindergarten No. 5: thermo-modernization works and modernization of the lighting and the installation of an energy management system;

School Commercial - main building: thermo-modernization works and modernization of the lighting and the installation of an energy management system;

Commercial School - gym: thermo-modernization works and modernization of the lighting and the installation of an energy management system;

Youth Culture: thermo-modernization works and modernization of the lighting and the installation of an energy management system;

III LO: thermo-modernization works, modernization and installation of lighting energy management system;

Pool MOSiR: thermo-modernization works and modernization of the lighting and the installation of an energy management system;

Building an orphanage: thermo-modernization works and modernization of the lighting and the installation of an energy management system.

Estimated total contract value excluding VAT: 25 849 510.16 PLN = 6 191 647.74 EUR.

The project will be implemented on the basis of an agreement for public - private partnership, assuming the division of tasks and risks between parties to the contract.

As part of the joint project implementation, Private Partner undertakes to finance, design and execution of works and maintenance and management of the resulting infrastructure over the period from 10 to 15 years - a period that will be clarified in the process of competitive dialogue.

It also assumes financial participation Public Entity in the joint venture on the principles established in the dialogue.

The duties of the Private Partner / Contractor under the project will include the maintenance and management of the energy economy.

Construction work

Gmina Miasta Sopotu | Published May 19, 2016  -  Deadline May 19, 2016
cpvs
45000000, 45210000, 45300000, 45331000, 45450000, 45453000, 45453100

Works

Construction work

PKP Energetyka SA w Warszawie – Oddział Usługi Zakład Północny w Sopocie | Published February 17, 2015
cpvs
45000000

Umowa

Cycle path construction work

Zarząd Dróg i Zieleni w Sopocie | Published October 23, 2015
Winner
Firma Budowlano-Drogowa MTM SA
cpvs
45233162

Complementary works for the construction of pedestrian and bicycle from the roundabout di Ergo Hestia Arena - Phase I - plantings parts, performance mosaic pattern of cobblestones - as agreed by the Conservator m.Sopotu.

Cycle path construction work

Zarząd Dróg i Zieleni w Sopocie | Published July 29, 2015
Winner
ASPERGO Maciej Dziechciński
cpvs
45233162

Work complementary to the rump. Reconstruction al. Polish Army in Sopot in order to extract the bike path -Construction the wall of resistance, widening the width of a pedestrian, removal of interfering green plantings parts.

Engineering design services for the construction of civil engineering works

Zarząd Dróg i Zieleni w Sopocie | Published July 7, 2016
Winner
Biuro Projektowo Consultingowe HydroEco s.c. A. Pieniążek, E. Felińczak, M. Felińczak
cpvs
71322000, 71311000, 71248000

Subject matter of this contract includes the development of a comprehensive, multi-branch Documentation Project entitled .: "Construction and reconstruction of storm water drainage network system in the area of ​​streets Abraham and Anders" and "Construction of storm water drainage in the street. Mick "with author's supervision during the execution of construction works.

The aim of the plans is to organize water and wastewater management within the streets Anders Abraham, Paderewski and Mickiewicz and improvement of road infrastructure, modernization of street lighting, which will significantly improve communication and increase road safety in this area of ​​the city of Sopot.

Cycle path construction work

Zarząd Dróg i Zieleni w Sopocie | Published July 8, 2015  -  Deadline August 14, 2015
cpvs
45233162, 45233220, 45310000, 45316100

The subject of the contract is works involving the construction of pedestrian and bicycle path on the section from the roundabout to ErgoAreny Hestia Sopot in place of the existing structured not the pedestrian. The task includes the execution of foot-cycle path with a width of 3.5 m over a length of 422,37m. The beginning of the tasks adopted at the end of bituminous pavement Hestia roundabout and the end - the inclusion of the existing road with openwork panels in the area ErgoArena.

Cycle path construction work

Zarząd Dróg i Zieleni w Sopocie | Published February 14, 2015  -  Deadline March 30, 2015
cpvs
45233162, 45233220, 45231000, 45316100, 45112710, 45231300, 45232310

Rebuilding al. Polish Army in Sopot on the section from the street. ks. Kordeckiego to the street. Brave to extract the bike path within the project entitled: Development of Communication Cycling Tri-City Agglomeration in 2007-2013 - the construction of a bicycle path pavement, sidewalks and murka stone, reconstruction of lighting, ducts, reconstruction and regulation of storm water drainage, sanitation and water supply works green, horizontal and vertical signage.

Construction supervision services

Gmina Miasta Sopotu, w imieniu i na rzecz której działa Zarząd Dróg i Zieleni w Sopocie | Published November 23, 2017
Winner
Konsorcjum firm: Przedsiębiorstwo Inżynieryjne ALFA Przemysław Marszałkowski – LIDER, Rejonowy Zarząd Inwestycji Człuchów Sp. z o.o. – Partner
cpvs
71520000, 71540000, 71311000

Box 86, CH-1000 Lausanne 12, Switzerland, and the third edition of English-Polish 2005.

All requirements for the provision of the Contract Engineer services for the above-described Construction Works are described in the Terms of Reference of the Contract, in particular in Part II - Description of the Object of the Contract.

Construction work for pipelines, communication and power lines, for highways, roads, airfields and railways; flatwork

Zarząd Dróg i Zieleni w Sopocie | Published August 18, 2015
Winner
Skanska Spółka Akcyjna
cpvs
45230000, 45232130, 45233220, 45231400, 45232000, 45233150

Object of the contract are the construction works consisting of: A. the modernization and increased retention in urban catchments the sewage DN300 / 400 Street. Kraszewski in Sopot, including replacement of pavements; B. The arrangement of rainwater in st. Poznan in Sopot; C. The construction of storm water drainage in the streets of Forest and Świemirowskiej in Sopot. Purchaser under the contract for implementation of construction works provides for supplementary contracts referred to in Art. 67 paragraph. 1 item 6 of the Public Procurement Law. Ordering a possibility of execution of the contract with the involvement of subcontractors.

Engineering design services for the construction of civil engineering works

Zarząd Dróg i Zieleni w Sopocie | Published April 14, 2016  -  Deadline May 24, 2016
cpvs
71322000, 71311000, 71248000

Subject matter of this contract includes the development of a comprehensive, multi-branch Project Documentation pn .: Construction and reconstruction of storm water drainage network system in the area of ​​streets Abraham and Anders and construction of storm water drainage in the street. Mickiewicz, along with author's supervision during the execution of construction works.

The aim of the plans is to organize the water and sewage management in the area covered by the contract, which has lead to improved drainage, rainwater drainage system located within the streets Anders Abraham, Paderewski and Mickiewicz and directing the flow of rainwater into the exhaust system B, the discharge of water streams Sopot into the Gulf of Gdansk. , The project also aims to improve road infrastructure, modernization of street lighting, which will significantly improve communication and increase road safety in this area of ​​the city of Sopot.

Construction work for pipelines, communication and power lines, for highways, roads, airfields and railways; flatwork

Zarząd Dróg i Zieleni w Sopocie | Published February 4, 2015  -  Deadline March 12, 2015
cpvs
45230000, 45240000, 45232150, 45232130, 45232410, 45233162, 45233220, 45231400, 45232000, 45112710, 45233150

The investment account for Construction Work involving the "Development of rainwater and snowmelt in the catchment area of ​​Stone Brook Pond, along with the modernization and increased Obodrzyców retention and revitalization of green". The Employer provides for the implementation of the main tasks of the investment in two stages: Obodrzyców with Obodrzyców tank modernization, reconstruction of the open trough in kindergarten and the construction of the underground tank Wejherowska.Termin the implementation of the first stage no later than 11/15/2015. Deadline for completion of the second stage is not then to 29/04/2016. The scope of works includes: Part hydrotechnical Wejherowska; b) the rebuilding of water storage reservoir "Pond Obodrzyców" in order to revitalize and increase retention capacities; Obodrzyców and Wejherowska, part installation: Wejherowo; Obodrzyców of property No. 42 to Kindergarten No. 4; c) pre-treatment unit assembly: Obodrzyców and Wejherowska - for storm water drainage ul. Luzycka Obodrzyców. d) reconstruction of the elements of water and sewage networks interfering with the planned buildings. Part of the road: a) reconstruction Obodrzyców Street between the intersection of the streets Cieszyńskiego- Kolberg to the intersection with the street Łużycką; b) the construction and reconstruction of the transportation system that supports the proposed scheme rainwater management in the basin snowmelt Stone Brook; c) reconstruction of the communication system of green spaces in the district of Stone Brook in Sopot associated with their proposed revitalization. Architectural part: a) land use in the area of ​​street Obodrzyców by cleaning up parks and execution of small architectural elements on the section from the inlet pipe to the storage reservoir to the intersection with the street Wejherowo; b) the revitalization of the area Kindergarten No. 4 in the area of ​​Stone Brook open trough. Lighting and electrical part: a) the demolition and construction of street lighting Obodrzyców; b) the demolition and construction of urban lighting in the area of ​​the square crossing the street Obodrzyców and Wejherowska; c) the construction of lighting pedestrian and cycling in the area of ​​open storage reservoir "Pond Obodrzyców"; d) the repair of the staircase lighting field on reaching the street Obodrzyców; e) the reconstruction of infrastructure electro-energy colliding with the planned buildings. Hi teletechnical: a) performance monitoring enabling tele part of the area covered by the project; b) reconstruction of telecommunication infrastructure colliding with the planned buildings. Hi gas: a) the reconstruction of the gas network elements colliding with the planned buildings.

Building construction work

Gmina Miasta Sopotu | Published February 23, 2017
Winner
Firma Handlowo-Usługowa Sardaw Marcin Plichta
cpvs
45210000

The contract is for the execution of works involving the completion of energy-efficient refurbishment of multi-family residential building at the Sopot Bonfires of Art located at ul. Lunar 3 / A, B and C in Sopot.

Cycle path construction work

Zarząd Dróg i Zieleni w Sopocie | Published July 10, 2015  -  Deadline August 14, 2015
cpvs
45233162, 45233220, 45310000, 45316100

Roboty budowlane w zakresie ścieżek rowerowych

Cycle path construction work

Zarząd Dróg i Zieleni w Sopocie | Published March 7, 2015  -  Deadline March 31, 2015
cpvs
45233162, 45233220, 45231000, 45316100, 45112710, 45231300, 45232310

Roboty budowlane w zakresie ścieżek rowerowych

Engineering design services for the construction of civil engineering works

Zarząd Dróg i Zieleni w Sopocie | Published December 15, 2015
Winner
Biuro Projektowo-Consultingowe HYDROECO s.c. Andrzej Pieniążek Edyta Felińczak, Marcin Felińczak
cpvs
71322000, 71311000, 71248000

Army Polish-Kilińskiego was to prevent the flooding of the lower terrace of the town of Sopot "along with the author's supervision during the execution of works. , The project also aims to organize road system along with the reconstruction of street lighting underground infrastructure, which greatly improve communication in this region of the city, at the same time improving the management of urban space. The detailed scope of the contract includes the execution of the following elements of the Project Documentation: - The inventory of existing state of the area covered by the contract - Construction Design, grocers, containing, among others, the technological and design, the technology of excavation, together with protection of adjacent buildings located in the area of ​​work, detailed hydraulic calculations for the proposed storm sewer system and projects the removal of collisions networks designed weapons underground and above-ground - geological documentation and geotechnical subsoil in an area in the implementation of the order, - The geological work together with the documentation concerning. execution of piezometers - Inventory and management of greenery - Sampling wodnoprawny - documentation concerning. assessment of the impact on the environment - Project of traffic during construction - Project Target Organization Movement - Project Executive grocers, containing detailed drawings - Technical Specifications Execution and Acceptance of Construction Works - Bill of Quantities - Estimate of investor - Sampling formal-legal with a color chart a collective and author's supervision over construction work carried out on the basis of the subject matter of this contract (max 50 stays) . Therefore, the responsibility of the Contractor will also include drafting an application for a building permit for the investment and obtaining all the necessary administrative decisions, agreements and opinions, which are annexed to the application for a building permit.

Sopot: construction work complementary to the Order podst.na Repair and reconstruction of the footbridge over the gorge in the street. Defenders of Westerplatte in Sopot

Zarząd Dróg i Zieleni w Sopocie | Published October 3, 2016  -  Deadline September 19, 2016
Winner
SAFEROAD KABEX Sp. z o.o., ul. Betoniarzy 32, 80-298 Gdańsk, kraj/woj. pomorskie.
cpvs
45221113

Construction Supplementary such as: execution of the strengthening of the slope riprap and planting ivy and execution of expansion joints railings footbridge ..

Construction work for pipelines, communication and power lines, for highways, roads, airfields and railways; flatwork

Zarząd Dróg i Zieleni w Sopocie | Published February 14, 2015  -  Deadline March 23, 2015
cpvs
45230000, 45232130, 45233220, 45231400, 45232000, 45233150

The investment account for Construction Work consisting of: Kraszewski in Sopot, including replacement of pavement, Poznań Sopot, Construction of storm water drainage in the streets of Forest and Świemirowskiej in Sopot. The secondary objective is to improve the condition of roads Kraszewski and Technology. Kraszewski in Sopot consists in performing the following basic elements of the Works, which include: The channel that the channel sections are designed for retention of rainwater (channel reservoirs - 10 pcs.) With a diameter of DN2000 and the total length L = 184.0m - Vreta = 555.69 m3. Construction of 22 pcs. Of typical concrete inspection chambers DN1200 and 36 kpl street inlets typical mountain type grate, and 1 set of linear drainage class D400. Reconstruction of the district heating network in the area of ​​intersection with the planned storm water drainage network. Reconstruction of street lighting, underground infrastructure protection at the intersections of the proposed storm water. Restoration of road surface over the entire width Kraszewski and entries on estates and sidewalks. Poznań Sopot consists in performing the following basic elements of the Works, which include: construction of the sewage DN500 DN200 with connections to the property and street inlets within a lane street Poznan - total length of the proposed channel rain: 79.0m. Construction of retention and drainage consisting of: retention and infiltration team consisting of 16 pieces. Chambers SC-740, with L = 2.17m, B = 1.30m, H = 0.76m each - retention capacity unit: V = 36.8 m3, well-retention rewizyjno DN1200 (5 pcs.), reinforced concrete chamber K1 internal dimensions of 2.60 × 2.50 × 1.80m, fitted with absorbing cushion 100 x 50cm. Poznan: surface reconstruction after sanitary works with cobble stone przebrukowanie recycled and the rest of the street, reconstruction of curbs and edges, surface restoration and post-session nawrotki entries at the end of the street pavement surfaces to restore the health of the works of washed gray paving tiles 30 × 30cm, replacement plates paving the area not covered by the sanitary works on washed gray 50 x 50cm. For superior channel will be enabled DN150 two connections from the property Poznan 1 and 3, the protection of underground infrastructure at the intersections with the proposed channel rain and connections. Forestry and Świemirowskiej in Sopot in its scope includes the following components of the Works: Construction of the sewage system with variable diameters from DN 160 to 500 PVC / PP with inspection chambers DN1200 and DN1500 and street inlets, drainage line, and connections to premises rainy Forest 2 and 2a, Construction of pre-treatment, consisting of a settler DN1500 V = 2.5m3, with additional equipment in the sleeve sorbent. Purchaser under the contract for Construction Works provides for the grant of supplementary contracts referred to in clause 1, item 6 Art.67 of the PPL Act. Purchaser notifies you to give the part of the area covered by the investment in question to another contractor who will carry out a contract awarded by another Employer, ie. By AQUA-Sopot Sp. z oo, associated with the reconstruction of water supply and sanitary sewage.

Sopot: Construction of car parking in the streets of the Warsaw Uprising and Haffner Sopot, in the framework of the project entitled: protection, restoration and protection of natural areas in spas Woj.Pomorskiego through the construction of infrastructure responsive tourist traffic and development and increase biodiversity in environmentally valuable areas in Ustka and Sopot, funded under the ROP for the province. Pomeranian for 2014-2020

Zarząd Dróg i Zieleni w Sopocie | Published October 3, 2016  -  Deadline September 29, 2016
Winner
EUROVIA POLSKA SA, Bielany Wrocławskie ul. Szwedzka 5, 55-040 Kobierzyce, kraj/woj. dolnośląskie.
cpvs
45233220, 45230000, 45100000, 45316100, 45233221, 45112710, 45231000

Construction of car parking in the streets Powst.W-O and Haffner Sopot.