Construction work for water projects

Waterschap Hollandse Delta | Published October 15, 2016  -  Deadline October 25, 2016
cpvs
45240000

water Construction

New construction consort Wells.

Waterschap Hollandse Delta | Published March 10, 2016
Winner
Ooms Construction BV
cpvs
45240000

2 ground on the island Wells, Perseverance and the Biersum are at the end of their service life and must be replaced. It was decided to modernize the drainage Wells among others the construction of a new pumping station in capacity which is big enough for all of Wells. Because it is built on a new location, the existing drainage can function until the new pumping station is realized. However, this makes it necessary that a new afferent main conduit (consort draft) is applied. This contract covers only the implementation of the specifications for the purpose of construction of the pumping station Putten. The realization of the pumping station tour and the possible decommissioning of the existing ground is not part of this tender. The work concerns the full realization of the new pumping station Putten, which should be realized in the Schuddebeurs Embankment in Spijkenisse.

Construction work for water projects

Waterschap Hollandse Delta | Published August 20, 2015  -  Deadline October 2, 2015
cpvs
45240000

The work consists essentially of: - working in and in the vicinity of a weir; - Implementation from 5 m wide strip of material on agricultural land in order to prevent structural damage; - Replacing and installing round culverts and box culverts; - Widening and new digging ditches; - The construction of bank protection mats; - The construction of bank protection of cloth with poles; - Removal and installation of bank protection of poles with boards; - Adapting level regulator works with and without automatic control; - Keeping a flush pumping station; - The construction of a siphon in the primary water with automatic steering; - Provisioning associated with cables and pipes; - The removal of trees and shrubbery; - Removing and installing gates and fences; - Small location remediate soil contamination by a bus message; - Demolition of an agricultural barn and share a dike warehouse with tiny asbestos.

Construction work for water projects

Waterschap Hollandse Delta | Published November 20, 2015  -  Deadline January 25, 2016
cpvs
45240000

Two pumping stations on the island Wells, Perseverance and the Biersum, at the end of their service life and must be replaced. It was decided to modernize the drainage Wells among others the construction of a new pumping station that in terms of capacity is large enough for all of Putten. Because it is built on a new site, the existing drainage can function until the new pumping station is realized. However, this makes it necessary that a new afferent main conduit (consort draft) is applied. This contract covers only the implementation of the specifications for the purpose of construction of the pumping station Putten. The realization of the pumping station tour and possibly decommissioning the existing ground does not belong to this tender. The work involves the comprehensive realization of the new pumping station Putten, which should be realized in the Schuddebeurs Dike in Spijkenisse.

Construction work for water projects

Waterschap Hollandse Delta | Published June 8, 2016
Winner
Aannemingsbedrijf A. J. Kuipers BV
cpvs
45240000

The work consists essentially of:

- Working in and in the vicinity of a weir;

- Implementation from 5 m wide strip of work on agricultural land with material to prevent structural damage;

- Replacement and installation of round culverts and box culverts;

- Widening and new digging ditches;

- The construction of bank protection mats;

- The construction of bank protection of cloth with poles;

- Removal and installation of bank protection of poles with shelves;

- Adjusting level regulatory structures with and without automatic control;

- The installation of a flush pumping station;

- The construction of a siphon into the primary water with automatic steering;

- Make provisions relating to cables and pipes;

- The removal of trees and shrubbery;

- Removal and installation of gates and fencing

- Small site soil remediation through a bus message;

- Demolition of an agricultural shed and share a dike warehouse with small asbestos.

Construction work

Gemeenschappelijke Regeling Nieuw Reijerwaard | Published October 15, 2016
Winner
Schotgroep Aannemingsbedrijf BV
cpvs
45000000

The work consists essentially of:

- Carrying out earthworks;

- Conducting duct work;

- Performing paving work;

- Applying wegbebakening;

- The application of drainage;

- Performing and other general work.

Construction work

Gemeenschappelijke Regeling Nieuw Reijerwaard | Published July 15, 2016  -  Deadline September 5, 2016
cpvs
45000000

The work consists essentially of:

- Carrying out earthworks;

- Conducting duct work;

- Performing paving work;

- Applying wegbebakening;

- The application of drainage;

- Performing and other general work.

Construction work

BAR-Organisatie (Barendrecht, Albrandswaard, Ridderkerk) | Published August 19, 2015
Winner
Van Rennes Elektrotechniek & Installatietechniek
cpvs
45000000

Work on the new building comprises the design of the multifunctional accommodation (MFA) Lagewei. The project has a volume of 2348 m² GFA.

Construction work for water projects

Waterschap Hollandse Delta | Published December 16, 2015
Winner
GMB Civiel BV
cpvs
45240000

The "Compensatory measures Kier Decision" includes the measures that are needed within the management of Hollandse Delta water to secure freshwater supplies Goeree-Overflakkee and Voorne-Putten after opening up in 2018 by Rijkswaterstaat of the Haringvlietsluizen (the Kier Decree). Besides the realization of the new water intake points and newly dug ditches to be widened and there is a transport provided for the supply of raw water to Goeree-Overflakkee. The compensatory measures Kier Decision to be carried out by WSHD Voorne-Putten be tendered as two parts: - CMK Voorne West, as traditional RAW cutlery (already in progress) - CMK Voorne East, as traditional RAW cutlery. The compensatory measures Kier Decision to be carried out by WSHD on Goeree-Overflakkee be tendered as three parts: - CMK Goeree East, as D & C contract - CMK Goeree West, as traditional RAW cutlery - CMK Goeree Middle, as traditional RAW cutlery. The work scope of the D & C contract "CMK Goeree East" consists mainly (not exhaustive) in the design and realization of: - intake facility near consort Koert, - siphons crossing harbor channel Middelharnis, - adjusting the potential (depending on design) effluent pipes WWTP Middelharnis (remove asbestos lead and cast iron pipe fitting new leadership), - construction zoetwatertracé Goeree East (Van Pallandt Polder) - siphon crossing harbor channel Dirksland, - the mechanical and electrical installations, 400 m bike path in the Van Pallandt Polder (completing it in built in 2005 but now dead-end cycle) - optional: extra measures to make drainage after flooding. The project management system, including its underlying processes, should be based on a quality management system, or in the case of a combination of any number of quality management, which is (are) certified by a duly accredited certification body based on the current version of the NEN -EN ISO 9001 or equivalent.

Construction work for water projects

Waterschap Hollandse Delta | Published May 5, 2015  -  Deadline June 1, 2015
cpvs
45240000

The Programme 'Compensation measures Kier Decision' includes the necessary measures within the management of Hollandse Delta water to secure freshwater supplies Goeree-Overflakkee and Voorne-Putten after opening up in 2018 by Rijkswaterstaat of the Haringvlietsluizen (the Kier Decree). Besides the realization of the new water intake points and newly dug ditches to be widened and there is a transport provided for the supply of raw water to Goeree-Overflakkee. The compensatory measures Kier Decision to be carried out by WSHD Voorne Putten be tendered as two projects; - CMK Voorne West, as traditional RAW specifications (already in progress) - CMK Voorne East, as traditional RAW cutlery countervailed Kier Decree which are to be implemented by WSHD on Goeree-Overflakkee tendered as three sub-projects; - CMK Goeree East, as D & C contract - CMK Goeree West, as traditional RAW cutlery - CMK Goeree Middle, as traditional RAW cutlery The work scope of the D & C contract "CMK Goeree East" consists mainly (but not limited) to design and realization of: - Inlet Supply pumping station near Koert - Siphon port canal crossing Middelharnis - The possible (depending on design) adapting the WWTP effluent pipes Middelharnis (remove asbestos cement pipe and cast iron pipe fitting new leadership). - Construction zoetwatertracé Goeree East (Pallandt Polder) - siphon crossing harbor channel Dirksland - The mechanical and electrical installations 400m cycle track in the Van Pallandt Polder (completed in 2005 built but dead-end cycle) - Optional extra measures to make drainage after flooding, this project management system including its underlying processes must be based on a quality management system, or possibly in the case of a combination of several quality management, which is (are) certified by a duly accredited certification body based on the current version of the NEN-EN -ISO 9001 or equivalent.

Construction and site preparation, installation Centrum West Ridderkerk - Foundation Woonvisie

Stichting Woonvisie | Published March 30, 2015  -  Deadline April 19, 2015
cpvs
45222000, 45222000

The project site is located at the edge of the center in the town of Ridderkerk. The project concerns the restructuring of an existing residential area. The work towards the outside - the subject of this tender - consist of two parts: the site preparation and site preparation, installation of the area. Site preparation should be achieved after the demolition of the existing buildings; The site preparation, installation after completion of the new building and follow the opleverschema of construction.

Construction and site preparation, installation Centrum West Ridderkerk - Foundation Woonvisie

Stichting Woonvisie | Published March 23, 2015  -  Deadline April 12, 2015
cpvs
45222000, 45222000

The project site is located at the edge of the center in the town of Ridderkerk. The project concerns the restructuring of an existing residential area. The work towards the outside - the subject of this tender - consist of two parts: the site preparation and site preparation, installation of the area. Site preparation should be achieved after the demolition of the existing buildings; The site preparation, installation after completion of the new building and follow the opleverschema of construction.

Construction work for water projects

Waterschap Hollandse Delta | Published November 24, 2016
Winner
GKB Realisatie BV
cpvs
45240000

The Program "Countervailing Measures Kier Decision" includes the necessary measures within the area managed by Hollandse Delta water to secure freshwater supplies on Goeree-Overflakkee and Voorne-Putten after Rijkswaterstaat opening in 2018 of the Haringvlietsluizen (the Kier Decree).

For more information see the website www.kierharingvliet.nl

As a result of the decision Kier brackish Haringvliet and serve the water intake points of Hollandse Delta water board and Evides Water to be moved. Besides the realization of the new water intake points are widened and new ditches dug and a transfer is made for the supply of raw water to Goeree-Overflakkee.

The compensatory measures Kier Decision procured as two projects carried out by WSHD Voorne Putten.

- CMK Voorne West, as traditional RAW specifications (already completed)

- CMK Voorne East, as traditional RAW bes ...

The content of this tender to the work in sub Goeree-Overflakkee Central, as shown on the drawings situation (Cutlery Annexes to the attached Specifications HD WAB 0126-06).

Construction work for water projects

Waterschap Hollandse Delta | Published July 31, 2015
Winner
Boskalis Nederland BV
cpvs
45240000, 45247230

The contract involves the dike reinforcement of the dike section Hoekschewaard South along the Hollands Diep and the Haringvliet.

Construction work for bridges

Waterschap Hollandse Delta | Published January 16, 2015
Winner
<CONTACT_DATA_WITHOUT_RESPONSIBLE_NAME><ORGANISATION><OFFICIALNAME>GKB Realisatie BV</OFFICIALNAME><NATIONALID>24304985</NATIONALID></ORGANISATION><ADDRESS>Middelweg 1</ADDRESS><TOWN>Barendrecht</TOWN><POSTAL_CODE>2992 SP</POSTAL_CODE><COUNTRY VALUE="NL"/></CONTACT_DATA_WITHOUT_RESPONSIBLE_NAME>
cpvs
45221100

This contract is integral maintenance marine engineering and civil engineering structures such as culverts, dams, trash racks, control boxes, bridges, and so on. Maintenance includes: - preservation work; - Installation and repair of steel structures such as: • stairways; • (bridge) handrails; • landings; - Installing, replacing and repairing culverts of concrete and plastic; - Repairing, replacing and cleaning trash racks; - Installation and repair of bridges and railings; - Various cleaning; - Replace, repair and maintenance of flood gates, valves and slide; - Various earthworks.

Other miscellaneous construction materials

Gemeenschappelijke Regeling Nieuw Reijerwaard | Published January 22, 2015
Winner
<CONTACT_DATA_WITHOUT_RESPONSIBLE_NAME><ORGANISATION><OFFICIALNAME>Martens beton BV</OFFICIALNAME><NATIONALID>20026454</NATIONALID></ORGANISATION><ADDRESS>Statendamweg 75</ADDRESS><TOWN>Oosterhout</TOWN><POSTAL_CODE>4905 AD</POSTAL_CODE><COUNTRY VALUE="NL"/><E_MAILS><E_MAIL>verkoop-mabe@martensgroep.eu</E_MAIL></E_MAILS><PHONE>+31 162422900</PHONE><URL>www.martensgroep.eu</URL><FAX>+31 162435784</FAX></CONTACT_DATA_WITHOUT_RESPONSIBLE_NAME>
cpvs
44192000

Concerns the supply of precast concrete products for the purpose of realization of the business New Reijerwaard in Ridderkerk.

Framework agreement "" Construction and quality water "- Hollandse Delta Water

Waterschap Hollandse Delta | Published December 17, 2014  -  Deadline September 18, 2014
Winner
A.K. Barendregt Aannemingsbedrijf B.V. 24218358 Kanaaldijk West 13 a, ZWARTEWAAL, 3238LM Nederland Telefoon: +31 181393473, Fax: +31 181393462 E-mail: ageblok@akbarendregtbv.nl, (URL): www.akbarendregt.nl
cpvs
45240000, 45240000

In section 3.3.1. of the tender documents is a summary given of the projects in the coming years (until 2017) to be achieved through the water and sheep that are queried by the exit framework agreement. Work to achieve these investment projects consist of the following: - Application of natural banks and water storage, with or without realizing landscaping (wet and dry) and earthworks; - Management and maintenance of natural banks; - Construction of small hydraulic and / or civil engineering works, such as culverts, dams, piling and the installation of shore protection and / or growth mats; - Creation and raising of paving and roads, such as asphalting work, paving, aanhelen and customizing plot entrances and installation of street furniture; - Installation of sheet piles; and - Other technical werkzaaamheden culture, such as applying Veeke rings, milling, cutting, drilling. Appendix 8 of the aanbestedingsleidraad specifications Waterlogging Lageweg Simonshaven attached which must be registered. In Part 2, below 1:04 of these specifications have been described primarily in the work which must be carried out. This includes: - Implement groundwork for achieving a nature friendly bank; - Supply and installation of foundations; - Installation of culverts; - Installation of fencing; - Removal and installation of fencing; and - The performance of additional services.

Construction work for water projects

Waterschap Hollandse Delta | Published September 3, 2016  -  Deadline October 14, 2016
cpvs

The Program "Countervailing Measures Kier Decision" includes the necessary measures within the area managed by Hollandse Delta water to secure freshwater supplies on Goeree-Overflakkee and Voorne-Putten after Rijkswaterstaat opening in 2018 of the Haringvlietsluizen (the Kier Decree).

For more information see the website www.kierharingvliet.nl

As a result of the decision Kier brackish Haringvliet and serve the water intake points of Hollandse Delta water board and Evides Water to be moved. Besides the realization of the new water intake points are widened and new ditches dug and a transfer is made for the supply of raw water to Goeree-Overflakkee.

The compensatory measures Kier Decision procured as two projects carried out by WSHD Voorne Putten:

- CMK Voorne West, as traditional RAW specifications (already completed);

- CMK Voorne East, as traditional RAW specifications (in progress already).

The compensatory measures Kier decision carried out by WSHD on Goeree-Overflakkee are / will be tendered as three sub-projects:

- CMK Goeree East, as D & C contract (already in progress-design);

- CMK Goeree West, as traditional RAW specifications (already in progress);

- CMK Middle Goeree, as traditional RAW cutlery.

Construction work for water projects

Waterschap Hollandse Delta | Published June 17, 2016
Winner
GKB Realisatie BV
cpvs
45240000

The Program "Countervailing Measures Kier Decision" includes the necessary measures within the area managed by Hollandse Delta water to secure freshwater supplies on Goeree-Overflakkee and Voorne-Putten after Rijkswaterstaat opening in 2018 of the Haringvlietsluizen (the Kier Decree).

For more information see the website www.kierharingvliet.nl

As a result of the decision Kier brackish Haringvliet and serve the water intake points of Hollandse Delta water board and Evides Water to be moved. Besides the realization of the new water intake points are widened and new ditches dug and a transfer is made for the supply of raw water to Goeree-Overflakkee.

The compensatory measures Kier decision which contracted to be performed by WSHD Voorne Putten as two subprojects;

- CMK Voorne West, as traditional RAW specifications (already completed)

- CMK Voorne East, as traditional RAW specifications (in progress already).

The compensatory measures Kier decision to be implemented by WSHD on Goeree-Overflakkee be tendered as three sub-projects;

- CMK Goeree East, as D & C contract (already commissioned)

- CMK Goeree West, as traditional RAW cutlery,

- CMK Middle Goeree, as traditional RAW cutlery.

The content of this tender to the work in sub Goeree-Overflakkee West, as indicated on the site plan.

This contract is designed after an European civil procedure in accordance with the Directive and to come ARW 2012 to an Agreement for the Work with a Contractor.

Works for complete or part construction and civil engineering work

BAR-Organisatie (Barendrecht, Albrandswaard, Ridderkerk) | Published May 18, 2016  -  Deadline June 20, 2016
cpvs
45200000

improve water quality and make it through the navigable waterway "Blue Connect".

The work consists essentially of:

- Close watercourses,

- Breaking element pavements,

- Breaking up asphalt,

- Remove base courses,

- Remove existing concrete culverts,

- Earthworks,

- Apply dewatering,

- Apply temporary sheet piling,

- Make concrete piles,

- Make concrete foundation floor,

- Affixing prefabricated culvert elements

- Apply foundation layers,

- Applying element pavements,

- Applying asphalt.