Call +44 800 9755 164

Public tenders for construction in Hungary

Find all Construction tenders in the world.
Finding business opportunities has never been easier.

Results for construction. Make a new search!

Construction work

Budapest Főváros XIII. Kerületi Önkormányzat | Published December 14, 2016  -  Deadline January 18, 2017

Service and residential building construction in Budapest, XIII. undeveloped property under Klapka utca, District 17 (27941/43. u.) No, the environment is rebuilding (27939th, 27941/8. 27941/9. 27942nd u.).

service providing residential and contract for construction of the Budapest XIII. District 17 under Klapka Street construction site, the following key quantitative data:

- Land area: 5390 m²;

- Built-up area 2 387.87 m²;

- Below ground level installation: 2 951.25 m²;

- Green Surface area: 1 903.46 m²;

- Total building. floor area: 10 m² 102.36;

- Parking: + 36 100 pcs.

Construction work

NIF Zrt. | Published December 28, 2016  -  Deadline February 13, 2017

Debrecen intermodal transport centers and related ancillary facilities design and construction tasks (PST Code: I000.01)

Füzesabony - Debrecen II. a main road 108 + Arrow Hadházi road junction at 923 km section of the temporary reconstruction.

The property topographical number 9555/5 42 325 m 2 useful floor area, two floors below background color basement + ground + 3 floors levels are above ground level 4 part of the building (including 386-seat parking garage also) includes public buildings reconstruction, construction of 3000 m² steel support structure of the glass roof construction and the complex design of the necessary workspace delimitation (résfalépítése ) and dewatering of approximately 25 000 m², demolition, about 11 200 m 3 amount of built urban environment.

Specifying the Community Intermodal Transportation Center (IKKK) and external utility privileges are associated with the construction of associated facilities:

o Medium Voltage networks;

o Low voltage network;

o Public lighting network;

o Small and medium pressure gas distribution pipeline;

o District Heating Supply Network;

o Water supply pipelines;

o Precipitation channels;

o sewer;

o Hydraulic Engineering;

o communication lines.

necessary for the performance of the No. 4 and No. 47. The main tasks of building roads for hiking, biking and road underpasses, as well as demolition of the existing bridge overpass Homokkerti felhajtóág.

The reconstruction of the main road No. 4 and No. 47, No. 4 main road and main road access to (private transport-level node) redevelopment.

4.1 .: The No. 4 highway 884.53 m contiguous (continuous-section) length of redevelopment, leading to falling about 430 m length of background color (1500 m³ of slurry wall construction), underpass providing road clearings under the tram track construction, development of two pieces of spiral roundabout.

4.2 .: No. 47 highway and No. 4 highway accession of redevelopment (0 + 741.78 -.. Section 0 + 975 km between c) existing indirect branches demolition and reconstruction of the rotation roundabout for access to be built in the No. 4 main road order.

establishment of 4 new traffic junction with traffic lights Traffic Management System, 1 traffic light traffic junction alteration and demolition 3 traffic light transport hub.

Rail (trams and trolleybuses) facilities and related equipment breakdown and a new tram track, headend, power supply, overhead line and signaling and safety equipment for construction:

o grooved rail-track breakdown Rafs: 645 vm;

o grooved rail Rafs superstructure construction: 850 vm;

o need to develop landing 1;

Move stop o 1 p.

Environmental Planning and park construction work, including grassing 40 000 m² to 15 000 m² of housing construction

providing rail plant in Debrecen railway station under construction, design, licensing and construction for the temporary replacement of the power supply equipment.

Füzesabony - Debrecen II. a main road 108 + Arrow Hadházi road junction at 923 km section of the temporary reconstruction.

involved an investment of means of transport: cars and trucks, bicycles, trams and buses (local, long-distance), trolley and pedestrian.

The areas of work covered inner area located in Debrecen execution.

Other additional design tasks:

- Dewatering,

- Temporary traffic engineering,

- Locating underground.

Other business activities:

- TRAFFIC temporary construction, demolition,

- Explosive Ordnance Disposal testing and disarming,

- Providing archaeological and other technical supervisors,

- Preparation of as-built plans.

The main way to No. 4 after its complete closure by the end of the 18th month, the Contractor is obliged to return the traffic for at least a temporary final in service license. (Part penalty pregnant deadline).

Contractor for the entire duration of the contract is required to find the vehicle Hajdu-Bihar County Correctional Institute Petofi Square entrance to ensure unrestricted accessibility.

Works covered by this procurement detailed description and a more detailed summary of the technical content of construction of the planned facilities include the procurement documents.

Construction work

Városliget Ingatlanfejlesztő Zártkörűen Működő Részvénytársaság | Published January 3, 2017  -  Deadline February 7, 2017

existing water supply systems in the City Park, 800 mm main line belt breakdown of Dn 400 mm Gov discharge line Ajtósi execution of Dürer road route of the road and Hungária krt Dózsa. between 74/75/79 and relocation of Public Transport trolley flight route of the road and Ajtósi Durrer Dózsa road and the 600-volt network reconstruction.

existing water supply systems in the City Park, 800 mm main line belt breakdown of Dn 400 mm Gov discharge line Ajtósi execution of Dürer road route of the road and Hungária krt Dózsa. between 74/75/79 and relocation of Public Transport trolley flight route of the road and Ajtósi Durrer Dózsa road and the 600-volt network, reconstruction of the procurement documents indicated below.

In addition to the trolley bus in the area of ​​City Park Ajtósi Durrer parallel to the line of a 800 mm water main pipeline also passes through belt, which must also be placed in the Ajtósi Durrer line.

In construction work must begin immediately because of the construction work in connection with the following conditions to limit the work:

- Water backbone construction works to be finished until 06.30.2017 on the basis of a statement by the Water Works.

- One of the venues FINA 2017 Swimming World Championships in aqueous City Park Ice Rink, so the start of the event the closing events of the road work can not be done,

- Park in Budapest facilities construction schedule of the project, which should start in autumn 2017 at the City Park Theatre and Dózsa György út construction of underground parking.

The content of the summary way procurement is the order of execution of the following works:

- To carry belt 800 mm main line breakdown of 98 m,

- To carry out DN400 mm discharge line Gov Ajtósi Dürer trail on the road and Hungária krt Dózsa. Between 612 m,

- Transfer of Public 74/75/79 trolley route flights, and 600-volt network, reconstruction of 6100 m.

Construction work

Paks Város Önkormányzata | Published December 31, 2016  -  Deadline February 13, 2017

The National Stadium Development Program under completion at Paks football sports facility construction and development works.

The National Stadium Development Program under completion at Paks football sports facility construction and development works.

In order to ensure continuous operation of the facility authorities carried out four phases of construction, the builder would like to place on the scheduled proceeding.

Implementation a) complete, turnkey construction on the basis of a valid building permit and other permits, as well as the detailed design documentation.

prepared and sanctioned b) the documentations submitted become very necessary project documentation.

Purchase c) In addition to the required building permits for construction and construction permits, property, services, user contributions.

all the permits required d) The startup, acquisition, ownership and service providers, operators contributions.

Quantitative characteristics of the design:

Demolished facilities:

Current főlelátó gross built-up area: 12.63 x 35.57 = 449.25 sqm.

Other elements built around the existing stadium (pavements, unused utilities, fences, smaller buildings, additional building and boxing hall building parts, mounted on stands).

Facilities to be held:

Contractor's job to protect the listed facilities, preservation during the construction works.

The basic data to be established football stadium:

Planned built-up area: 932.7 m² 3.

Planned paved surface: 6 557.43 m².

Planned total useful floor area of ​​2 266.17 m².

of which:

- The bleachers 1 719.71 m²,

- B grandstand 405.20 m²,

- C grandstand 59.67 m²,

- V grandstand 81.59 m².

Maximum building height: 7.94 m.

Precast concrete structures: 930.8 m³.

Steel supporting structure: to 165.33.

Other service facilities:

service roads, parking lots, sidewalks, installation of utilities, environmental planning, establishment locsolókút within the plot.

The construction work planned basic function:

- Football Stadium;

- Ticket offices, dressing rooms, maintenance areas, by sector canteens and toilets,

SKY-boxes, the VIP grandstand,

- Crafted media premises,

- Server operations management offices, meeting rooms.

Schedule:

Execution date of delivery of the work area (within 5 days of signing the contract) technical handover procedure completion, and not a final occupancy permit obtaining 120 days.

The work area will be transferred to the beat I, at the same time.

III. pace associated workspace handed over to 2016-17. It will be made within five working days after the last round of the year NB1.

The workspace is opened in Annexes I and II. days after the rate of occupancy permit becomes final will be held.

Match Day 3 hours before the match start of the work to be completed, the work area must be closed and deleted.

Construction work

Pécsi Tudományegyetem | Published December 31, 2016  -  Deadline February 13, 2017

The University of Pécs Faculty of Medicine partial renovation of existing academic building and completion of the associated new education and research wing of the building complex design and construction works.

Faculty of the University of Pécs Medical existing academic building has been partially updated and the related new education and research wing construction, the Medical Campus in mid-located park, as well as building and related expansion of green areas reconstruction, modernization, 308 pieces of surface and underground buildings car park is subject to investment , environmental planning, and related service road renovation and utility development projects within the property and the supply of related design tasks.

The objectives of the investment and the volume is summarized in the following table:

Development Goal Target Volume.

New Education and Research Infrastructure Construction of a new wing of 11 000 m².

Parking lots and construction of the new wing Campus 308 pieces.

Renovation of existing priority areas of education and community Theoretical Building 5000 m².

Renovation of Existing Power System Theoretical Building backbone network.

Pathology complete renovation and expansion of existing Theoretical Building 2400 m².

replacement of windows and facades of existing related Theoretical Building 10 000 m².

Environmental planning, landscaping Location (Medical Sciences Campus) 15 600 m².

Utilities and Utility Improvements precipitations Location (Medical Sciences Campus).

lab, part of the acquisition, as well as classroom / special classrooms / lecture hall design of floor area in excess of III.1.3./M1. points B and D specified amounts of PPA. taking into account § 65 (5) of the well.

Railway construction works

NIF Zrt. | Published December 30, 2016  -  Deadline January 20, 2017

Determination of contract:.

Subject: '(. Excl) - (. Bez) a contract to V100.32 Püspökladány Ebes track section of line construction and interlocking design and construction works. "

Construction work for bridges

NIF Zrt. | Published December 13, 2016  -  Deadline January 19, 2017

Komárom Komarno context of cross-border Danube bridge construction works of a contract.

Construction work for bridges

NIF Zrt. | Published January 14, 2017  -  Deadline January 24, 2017

Komárom Komarno context of cross-border Danube bridge construction works of a contract.

Construction work

Semmelweis Egyetem | Published January 6, 2017  -  Deadline January 30, 2017

Construction contracts under the KEHOP-5.2.4-15-2016-00004 identification number of projects in the works to carry out the modernization of energy Kútvölgyi Clinical Array, which is the Hospital Clinic Building and the four-story wing of the facade thermal insulation, stone cladding, doors and windows and replacing the shade structures the modernization of the cooling system and the modernization of energy at a time, into strength necessary technical work to be performed includes option also includes a pie clinic building and the modernization of the economic wing of energy.

The detailed definition of the work to be done working drawings, specifications and budget proposals as part of the tender documents contain.

Construction work

Nemzeti Sportközpontok | Published December 29, 2016  -  Deadline February 21, 2017

Dunavarsány Central - Hungarian Olympic Centre design and construction of I-II. the pace.

The implementation of the development planned in several phases.

The subject of this acquisition I and II. Implementation schedule: Dunavarsány Central - Hungarian Olympic Centre design and construction I.-II. schedule, which includes the following tasks:

Design tasks:

- Based on the approval of the plan, provided the preparation of design documentation, licensing, permits, contributions or statements provided the necessary legislation on the acquisition,

- Contribution to an authorization, charging and management plans on the basis of power of attorney ÉTDR system,

- Preparation of detailed design documentation (without priced and unpriced, itemized budget, the built-in furnishings and built-in equipment, Mobilia), the Tender instructions and public document requirements of properly, in compliance with the Hungarian technical requirements of laws and regulations at all times in effect, in force the standards of form and content requirements, according to expectations,

- Ensuring the designer's leadership in design closure.

The amount to be delivered Plans: 3 copies on paper, Hungarian and .pdf / A; pdf; .dwg format or three copies of a CD / DVD.

Design tasks:

I pace.

1. Establishment of a new pool: accommodate 15x25 m swimming pool and a 6x10-meter warm-up pool 1750 m² facility, together with the associated server rooms.

Interior remodeling of existing facilities: Carry out internal restructuring works 460 m² floor space.

3. Establishment of a new roof and roof terrace Existing rear, above the dining area of ​​342 m².

4. New roof the valves: a new building next to the existing main entrance, 57 m² floor space (architectural - structural works).

II. The pace.

1. The establishment of a new sports hall.

26x46 m size - can accommodate handball court - 1550 m² facility, together with the associated server rooms.

Green Park development and spatial planning.

Road and car park building (1115 m²), paving (240 m²), spatial planning (1262 m²).

A further task: the acquisition of final occupancy permits.

For more information on the technical specification.

In such a case "or equivalent" should be understood that demonstrate the equivalence of the contractor will.

The construction site endowments, and the expected completion date taking into account the number of contractors performing work at the same time taking into account the organizational conditions are not possible.

Railway construction works

NIF Zrt. | Published December 29, 2016  -  Deadline February 15, 2017

within the framework of a contract between Szeged and Hódmezővásárhely construction of tram-train, light rail supply works design and construction tasks.

The rail line between road design and construction of Hódmezővásárhely Hódmezővásárhely People's Garden and large stations, and between Szeged and stop Roch Roch Branch.

Hódmezővásárhely light rail line design and construction work.

Hódmezővásárhelyen 3.3 km long single-track tram line construction, five seats and one stop végállomással.

On this section will establish a 600 V DC overhead line network (complete system), including converters, as well as the signaling and interlocking system deployment as well.

Szeged Roch light rail line design and construction work.

Related other ancillary works (peronépítés, level crossings fences etc).

The tasks are specified in the tender documents.

Contracting Authority draws the attention of the bidders that this procurement process in respect of the design task is construction plan level planning task.

Contracting authority shall also inform the bidders that the final building permit plans and permits are available.

Construction work

Nemzeti Sportközpontok | Published December 29, 2016  -  Deadline February 16, 2017

Gödöllői swimming pool design and construction of Phase I.

The implementation of the development - three pool competition and implement training pool - planned in two phases.

The present implementation of Phase I of the acquisition, in which two pool (25X50 meter competition pool and a training pool 6X10 m) the investment is realized.

Design tasks:

- Preparation of design documentation for authorization on the basis of approval of plan to be included in the tender documentation, permits, contributions or statements provided the necessary legislation on the acquisition,

- Contribution to an authorization, charging and management plans on the basis of power of attorney ÉTDR system,

- Preparation of detailed design documentation (without priced and unpriced, itemized budget, built-in furnishings and built-in equipment, Mobilia), the Tender instructions and procurement documents requirements of properly, in compliance with the Hungarian technical requirements of laws and regulations at all times in effect, in force, requirements of form and content requirements, according to expectations,

- Ensuring the designer's leadership in design closure.

The amount to be delivered Plans: 3 copies on paper, Hungarian and .pdf / A; pdf; .dwg format or three copies of a CD.

Design tasks: building Indoor swimming-purpose building complete, turnkey design, the related technology pool, landscaping, outdoor utility building projects, as well as with the acquisition of non-occupancy permit.

The larger competition pool, a 25X50 meter, and a smaller training pool, 6X10 m.

Useful floor area of ​​Phase I: 6 778.62 m².

For more information on the technical specification.

In such a case "or equivalent" should be understood that demonstrate the equivalence of the contractor will.

Tramline construction works

BKK Budapesti Közlekedési Központ Zártkörűen Működő Részvénytársaság | Published January 7, 2017  -  Deadline January 26, 2017

Pest side extension and construction of tramway line 1 reconstruction work in Etele Square.

Purchase Road construction machines - Corrigendum

Magyar Közút Nonprofit Zrt. | Published December 19, 2016
Purchase Road construction machines - Corrigendum

Railway construction works

NIF Zrt. | Published December 28, 2016  -  Deadline February 9, 2017

In order to ensure the long-term additional drainage works export planning and implementation of the railway track Balatonvilágos housed stability of loess wall.

In order to ensure the long-term additional drainage works export planning and implementation of the railway track Balatonvilágos housed stability of loess wall by performing the following duties and facilities construction and design:

1. railway track housed, located in loess slope and ancillary dewatering and drainage embankment to ensure the dewatering facility, inclusive implementation;

railway within the framework of the settlement environment 2. Additional dewatering facility alley parallel sidewalks and life safety fence construction;

3. loess have railway crossing drainage capacity building.

The length of drainage water should be drained into the recipient (Balaton).

The loess wall drainage carried out by a built in the 1970s, deep drainage tunnel, but this facility is not provided to all Layer ( "water floor") waters draining, so the long-term to ensure the necessary construction of additional drainage facility of the rail track housed loess wall stability of.

The loess crosses a railway track in Balatonvilágos in level crossing, which is the recipient of drainage is not solved, the drainage capacity additions and the construction should be carried out.

For these installations must perform the following planning tasks:

- Permitting plan preparation,

- Process the authorization process - to obtain a building permit,

- Contractor's planning,

- Implementation planning,

- Qualification documentation.

Major quantities envisaged:

- Deep drainage system construction: 7200, m

- Construction of a new underground seepage: 1950 m,

- Recipient collected water management and rainwater Construction: 1500 m.

The task included a detailed description of the procurement documents.

Road construction works

NIF Zrt. | Published December 3, 2016  -  Deadline January 19, 2017

M7 - 710 c. within the framework of the main road junction, 710 highway construction project contract for wiring (K071.01).

The contractor (Contractor) task also includes the following design, permitting and construction tasks:

- Budapest - Balaton bicycle route of the transfer of planning, licensing and construction of No. 710. The main road and the 7205th no. roundabout point.

The works constitute an indivisible service.

Road construction works

NIF Zrt. | Published January 6, 2017  -  Deadline February 7, 2017

7-710. s. within the framework of the main road junction, 710 highway construction project contract for wiring (K071.01).

The contractor (executor) is also responsible for the following design, permitting and construction tasks are: Budapest-Balaton bike path of the transfer of planning, licensing and construction of No. 710. The main road and the 7205th no. roundabout point.

The works constitute an indivisible service.

Catenary's construction works

NIF Zrt. | Published December 23, 2016  -  Deadline February 7, 2017

Determination of contract:.

"Szabadbattyán - Tapolca - Keszthely implementation bottlenecks challenge, electrification and centralized traffic control around the lake Phase I (Szabadbattyán-Aszófő)" project overhead line construction, railway construction and additional works of design and construction.

framework contract for the "Szabadbattyán - Tapolca - Implementation of Keszthely bottleneck challenge, electrification and centralized traffic control around the lake Phase I (Szabadbattyán-Aszófő)" project overhead line construction, railway construction and additional works of design and construction, the following main quantities:

Szabadbattyán - Aszófő electrification of the railway line, 50 Hz 25 kV AC overhead electrical design and construction of 60 km .;

Electrical substation design and construction of two locations;

transformer provided by the expansion and redevelopment of Customer Szabadbattyán existing 120/25 kV substation, transmission line construction in the feeding phase limit;

Aszófő existing 120/25 kV substation expansion for MAV provided by Customer transformers, power supply phase construction of the border;

Exchange Heating Design and construction of 42 bypass group;

Optical Cable Design and Construction (part vasútvillamosítás) 60 km;

5. Consolidated train operation control system is installed (as part vasútvillamosítás);

Catenary power control (FET) Establishment (part vasútvillamosítás):

6.1. Station 8;

Phase Cross: 3;

Bypass installation or replacement, substructure reinforcement:

Polgárdi industrial sites Station: 4 groups;

Polgárdi Station: 2;

Csajág station: 5 groups;

Balatonkenese station: 4 groups;

Balatonfűzfő station: 4 groups;

Balaton station: 4 groups;

Alsóörsi station: 5 groups;

Balatonfüred station: 12 groups;

Aszófő Station: 2;

Track construction substructure reinforcement: 11,5 km;

Strengthening local substructures: 700 vm;

Widening Alépítménykorona: 1900 vm;

11 Ágyazatrostálás 8750 vm;

Edilonos track construction system: 180 m;

Peronépítés (SK + 55 cm magasperon small battery cover 250 m in length):

13.1. Középperon station: 9;

Stops: 7;

Paved ditch construction: 4800 m;

Leakage System Construction of 14 km .;

One or multiple track crossing, providing level crossing level crossing, pedestrian and duty construction and reconstruction:

Rail and road crossings to ensure crossing 29 group;

providing rail-pedestrian crossing pedestrian crossing 23 group;

platform approach to providing pedestrian passage 11 group;

16.4. Station operating passage: 3 groups;

Peronaluljáró Balatonfüred renovation of the station;

Peronaluljáró Csajág renovation of stairs, and Balatonfüred stations;

Installation of platform lifts for disabled approach and Balatonfüred station: 4;

Small works of art construction / reconstruction: 3;

Stairs and ramps Reconstruction Balatonakarattya stop there;

Bridge Insulation works Renovation of objects: 2;

Railway perontető refurbishment / redevelopment Balatonfüred station;

Stations are installing shelters: 21 pc;

Asset protection, installation of fire alarm systems in buildings admission: 7;

Alsóörs power station design office;

Balatonfüred Kofi station design center;

28 Stations remotely control the station building 8;

29 station interlocking in accordance with, the construction phases, 8. station;

standardization of public utility crossings;

Create and export licensing and combined plans for implementation.

Library construction work

Makó Város Önkormányzata | Published December 22, 2016  -  Deadline January 31, 2017

construction of streets and squares and rehabilitation of the environment of the Mako József Attila Public Library's new building.

The construction of József Attila Public Library Makó designed organic architecture of the new building custom reinforced concrete and wooden structures, windows and doors, as well as building streets and squares for the rehabilitation of the environment.

The present construction investment is not part of the demolition of the old building and the construction start of an empty, fenced area is bounded by the contractor's disposal.

Library building construction:

Implemented construction works (construction).

Building permit number: CS-02D / 01 / 435-17 / 2016th

Library building construction result in a total built area (ground floor + attic + terraces): 1 938 m².

for the new directory squares and streets rehabilitation:

Implemented construction works (construction and demolition).

Road construction.

The number of construction permits: CS / path / 147/23 / 2016th

- Demolition work,

- Paved roadway construction and térköves 1114 m long,

- Bicycle path 634 m long, 2 m wide,

- Sidewalk construction: 2500 m length,

- Passenger waiting area construction of 351 units,

- Bicycle racks 180 pieces + 113 seats scattered térköves design,

- Construction of pedestrian crossings at 4,

- Accessibility of tactile pavements.

Downpipe

reconstruction of existing, closed-drainage system is 1803 m long, connecting pipelines, replacement of 481 meters.

Drinking reconstruction:

- Main and distribution line replacement length of 2257 m,

- Replacement of 594 meters of associated turn lead connection,

- Replacement of 10 fire hydrants,

- Installation of 21 pieces of valve reconstruction of existing mines.

IT replacement cables, aknaemelések.

Deák Ferenc utca cables for air induction and Invitel Telecommunications Zrt. Underground network pump of raising the level of 37 db, respectively. Replacing.

Reconstruction of heat and hot water lines:

- Deák Ferenc street, Pulitzer promenade 1650 meters in length,

- Connection of the new library district heating and hot water system.

Library electricity and water supply, sewage disposal, storm water drainage.

Water supply:

- Replacement of 594 meters of associated turn lead connection,

- Replacement of 10 fire hydrants,

- Installation of 21 pieces of valve reconstruction of existing mines.

Fountain and Fountain.

Store drinking fountain in front and four pool fountain in front of the market building, connecting their public utilities.

Electricity Network Rehabilitation:

- Install Galaxy 20/1 000 kVA transformer,

- Public of 20 kV and 0.4 kV network, rehabilitation, wardrobe changes,

- Rink's energy supply,

- A group of cabinets rákötéssel construction of new retail network.

modernization of public lighting - replacing.

162 LEDs - installation of street lighting columns and cable routing, gateway and lighting.

Horticultural irrigation system kiépítéssel:

- 43 tree felling, planting a total of 75,

- Install shrubs, grass,

- Automatic irrigation system, 10 200 m² from 10 m3 / h of water demand.

Building construction work

Széchenyi István Egyetem | Published January 14, 2017  -  Deadline January 25, 2017

design and construction plan of making a contract to emerge from the Széchenyi István University ED_15-1-2015-0012 contract No. flagship project of the government decision to be implemented "on the subject.