Road construction, bridge construction, utility trenches, TW-line, AW channel.
Earthworks, Road Construction, Underground drainage, construction of 2 bridges and a rainwater treatment plant, reconstruction of a stormwater treatment plant, drinking water supply, pressure sewer, Earthworks for gas pipeline and telecommunications cable
BT 0 - rata per client
BT 1 to 7 and 9 proportionately -. TLBV
BT 8 and 9 proportionately -. City administration Neustadt adO
BT 10 - Stadtwerke Neustadt Orla GmbH
BT 11 - German Telekom GmbH
BT 12 to 14 - Zweckverband water sewage Orla.
Construction for: 2014: - Erection of railway power line str. Nord (approx. 23 km) between the Eischleben and Wolfsberg subdivisions as well as integration into existing 110 kV railway power line in the Eischleben site with connections. (Part of the community road with 380 kV line Vieselbach-Altenfeld, approx. 4.5 km, this section is erected by the client of the 380 kV line). Complete work Eischleben- Errichtg. Blockunterwerk Wolfsberg in the railway station Ilmenau-Wolfsberg2015: - Construction of the access road. To the substations Eischleben and Wolfsberg with sufficient load carrying capacity for heavy load transports to the substructures of the switchgear Niederfüllbach (location at the branch Weißenbrunn aF) with simultaneous adjustment. Of the Untersiede Ebensfeld (supplementary equipment for NBS) - Erection of the switching post Dörfles-Esbach2016: - Errichtg. The traction current line tr. South (approx. 23 km) in the area of LK Coburg and Sonneberg- erection Blockwerk Roth.
UAE No. 8: Ecological construction supervision.
The LEG Thuringia intends to develop the large industrial area IG-5 Waltershausen-Hörselgau on approx. 180 ha in 2 construction phases. The subject matter of the procedure is the awarding of the project management services for the complex infrastructural development first of the first construction phase, which covers approx. 120 ha. This includes planning for the construction of traffic facilities, including lighting for wastewater disposal plants (contaminated and rainwater) and for drinking and extinguishing water supplies, as well as measures for off-road modulation including line relocations and compensatory and substitute measures. The overall measure is publicly funded by the "Joint Task for the Improvement of the Regional Economic Structure" (GRW). The estimated investment costs are about 32 000 000 EUR net.
The following project taxes are to be provided for the development measure:
For a detailed description of the individual services, please refer to the task description in the order documents under I.3.
The existing industrial area "Kölleda-Kiebitzhöhe" will be expanded in the area of the development plan 1/02.
The envisaged enlargement is approximately 64.6 ha. Part of the extension are measures for the construction of transport facilities incl. Lighting, disposal of sewage incl. Wastewater treatment plant expansion, for drinking water and fire water supply and Baufreimachung. The estimated investment cost will be approximately 25.75 million EUR net. The required services to site supervision to be awarded with the present tender.
The development measure is funded by the Joint Task "Improvement of regional economic structure" (GRW).
Construction supervision on the basis of the performance image of Structures performance phase 8 HOAI Special Leistungennach plant 12 no. 12.1 and to the performance image transport systems performance phase 8 Special services according to HOAI system 13 no. 13.1.
Planned workforce: construction supervisor, deputy Bauüberwacher and technicians. For details, see specifications in the system of the draft treaty.
Thüringer Energie AG is planning to expand the main administration of its main location in Schwerbornerstrasse in the state capital Erfurt to a TEAG campus.
2,000 mAs a result of this building situation, a special foundation with drill piles is planned.
specifications
Examples of preparatory actions:
Geotechnical reports,- company-internal construction site equipment,
200 mDrilling:
600 to 900 mm, drilled drilled: 25 m depth, 20 m depth, 15 m depth, 10 m depth,- Disposal of the drill material (partially contaminated) and the pile tips.
The pile heads are concreted by the body shell.Technical requirements, in particular:
- excavators,
- drilling technology,
- trucks,
- wheel loaders,
- construction site containers,
- Sharpener.
A detailed description of the performance will be made available to the bidders after the competition has been carried out.
Scheduled period of performance:
01.02.18 - 16.03.18 Factory planning
12.03.18 - 23.03.18 Construction site equipment
26.03.18 - 01.06.18 Special foundation.
Construction of district heating routes in Erfurt: Blumenstraße, Borntalbogen, Born Talweg.