Fv 545 Stord's west side - Fv 545 Sagvåg bridge

Statens vegvesen Region vest | Published November 24, 2014  -  Deadline January 8, 2015
cpvs
45221110, 45220000, 45221000, 45221100, 45221111, 45233000, 45233100, 45233320, 45236000

Project Fv 545 Sagvåg bridge is a complex project with the establishment of new bridge structures on the side of existing Sagvåg bridge, road improvements, the creation of sidewalks and universal design of bus bays associated road project. There will also be edge beam of concrete on natural stone as well as the erection of bridge parapets and Noise on natural stone. The project is part of the toll package Stord's west side. It will also be built on existing road lighting installations and once road system. The outdoor areas and walking road systems must be adapted to the new vegkurvaturen and local exits must be decontaminated and adapted to the new road alignment. Work will be performed while existing road network and existing bridge will be in operation as county.

Analysis Program for static and dynamic analysis of bridge structures

Statens Vegvesen | Published November 3, 2017
cpvs

Buyer wishes tenders for:
Analysis Program for static and dynamic analysis of bridge structures.
The purpose of the contract is to modernize the NPRA portfolio of analysis software (static and dynamic analysis of bridge structures - load effects).
For this procurement will be entered into a contract with one supplier.

Purchase of planning and engineering services for bridge structures on floating foundations of Halsafjord og Romsdal

Statens vegvesen Region midt | Published February 22, 2016
Winner
Teknisk Data AS
cpvs
71300000, 71311000, 71312000, 71315200

Buyer wishes tenders for engineering assistance in the form of cooperating and providing training for everyone working with hengebrukonstruksjon on liquid foundation over Halsafjord.

The purpose of the contract is to develop a concept for the crossing of Halsafjord in the context of the research work related to ferjefri E39 in More og Romsdal organized by the Awarding Authority.

The client wants the procurement assistance supply and cooperate to make an assessment of a concept with a combined floatation and hengebruløsning, and develop a calculation model in RM Bridge.

Purchase of planning and engineering services for bridge structures on floating foundations of Halsafjord in Møre og Romsdal

Statens vegvesen Region midt | Published January 21, 2015  -  Deadline March 9, 2015
cpvs
71300000, 71311000, 71312000, 71315200

Buyer wishes tenders for engineering assistance in the form of working and to provide training for all working hengebrukonstruksjon on liquid foundation over Halsafjord. The purpose of the contract is to develop a concept for the crossing of Halsafjord in the context of the research work related to ferjefri E39 in Møre og Romsdal organized by the Awarding Authority. The client wants the procurement assistance connecting and collaborating with to undertake an assessment of a concept with a combined floatation and hengebruløsning, and develop a calculation model in RM Bridge.

Construction worker Jøkelfjord bridge

Kvænangen kommune | Published April 19, 2016  -  Deadline May 19, 2016
cpvs
45221100

Based on inspection of Jøkelfjord bridge in Kvænangen after Manual 136 (NPRA) has decided to take action. The work includes rehabilitation of existing steel beams, replacement of concrete slabs with gratings and replacing railings and the establishment of regulatory drawdown / endings. It is made classification and static calculations of the beams. Employer reserves the financing and the project is within the financial limits set by the council and will consider this when quantity-based offering available. It may be appropriate that all or part of the project expires. The work is thought organized as a turnkey provider that affiliation the necessary expertise to undertake the project.

11-0535 Erfjord bridge maintenance in 2016

Statens vegvesen Region vest | Published August 12, 2016  -  Deadline September 2, 2016
cpvs
45000000, 45221115, 45341000, 45316110, 45221100

Erfjord bridge will be partially rehabilitated with scroll:

Shift Ning of hanger, new railings, new road lighting and new joints

Sokna Strait bridge, Parsell: Fv. 586

Statens vegvesen Region vest | Published June 30, 2015  -  Deadline August 19, 2015
cpvs
45000000

Replacement of damaged beam of 32 meters, kappestøp, mechanical concrete repair 5,000 liters, vannmeisling 15000 liter replacement of 170 meters bridge parapets.

Rehabilitation 2014 Hundvin bridge, Lindas Municipality

Lindås kommune | Published October 8, 2014  -  Deadline October 28, 2014
cpvs
45000000

Steinvelbrua with stone wall damage. It will be drilled into the steel core piles and added new bridge deck of precast concrete elements. New railings.

Concrete rehabilitation and replacement of railings Skjærnøysund bridge

Statens vegvesen Region sør | Published March 11, 2016  -  Deadline April 5, 2016
cpvs
45000000, 44114000, 45340000

Works include concrete restoration, surface preparation of concrete and replacement of guardrails on Skjernøysund bridge.

Estimated quantities for the main elements of the agreement:

- Injection Mortar Ling: Ca. 2606 liters

- Surface treatment of concrete: Ca. 1308 m2

- Replacement of bridge parapets: Ca. 232 m

- Safety barriers Ca. 186 m

Pedestrian bridge over the Vaal 2015 - Assembly

Ringebu kommune | Published November 18, 2014  -  Deadline January 22, 2015
cpvs
45221113, 45000000, 45200000, 45221000, 45221110

The work includes working with the building (laminated timber) for new pedestrian and bicycle over Vaal. Work on the ground and foundation performed as a separate contract. It is planned that the bridge will be completed during 2015. The foundation work has a deadline to be completed in June / July 2015. Most of the work for access roads and rounding around foundations must be assumed that performed after the bridge is fitted. Because of the division into two contracts so you must expect coordination between each of the contracting parties. Works for ground and foundation exists with the notice number 123923.

Route 13 Skjelvik, new bridge after floods

Statens vegvesen Region vest | Published November 8, 2013  -  Deadline December 5, 2013
cpvs
45000000

Contract work includes construction of concrete bridges consisting of in situ and precast abutments brubjelker over skredløp by Skjelvik in Odda municipality, approx. 10km north of Odda center (Hp06 - 5,020 km). Existing road "tied together" with the new bridge and it should be performed bottom and side overstretching of skredløp around bridge structures. In addition to the establishment of a new road to neighboring property. The work will be carried out based on prepared drawings. CPV: 45000000.

E10 Tjeldsundet bridge - Rebuilding stock and joints

Sted: hele Norge | Published February 28, 2018
cpvs
45221111

19-0670 Tjeldsundbrua is exposed to damage to alkaline reactions. This leads to a considerable extension of the bridge, which has led to the opening of the openings. There have been several repairs / reinforcements on storage and joints. In 2017 an emergency repair was carried out on joints and storage axes 18. The work involves the continuation of this work with the rebuilding of bridge storage, temporary and new warehouses, horizontal construction of the construction, water milling, new fuge etc. The work must be carried out in a certain order .

E16/Rv2 Kongevegen — Tjernsbergs veg, Main contract.

Statens vegvesen Region øst (The Norwegian Public Roads Administration. Region east) | Published July 4, 2015  -  Deadline September 7, 2015
cpvs
45000000

The contract work is on the E16/national road 2 between Kongevegen and Tjernsberg veg in Kongsvinger municipality, just north of the centre of Kongsvinger. This stretch is approx. 2.2 km and the site stretches from profile number 350-2100. The project will be implemented model-based. Diversions and temporary bridges used in this contract have been constructed in a preparatory contract. This contract work comprises, amongst other things: — Take over of the site with diversions and temporary bridges, the accompanying work warning plan, signs and protection, operation and maintenance of the site as if it was the contractor's own. — Moving the necessary cables and pipelines for the site work — New surface water system for new installations and adaptations to the existing system. — Construction of 2.2 km new foot and cycle path from Kongevegen to Tjernsbergs veg — New roundabout in the junction E16/national road 2 x Kongevegen — New Norsenga bridge over the railway, Solørbanen and Grensebanen. — New Vingersnoret bridge and the river Noret — Height adjustment of the road line from Kongevegen to Masterudvegen where the road body shall also function as flood protection — New street lights, noise reduction screens, planting — Necessary side measures, alterations to local roads and access roads — Demolition of temporary bridges and the accompanying diversion roads These areas shall be returned to how they were before the work started in the preparatory contract. The model for the project will show how these areas shall be prepared. — Norsenga bridge goes over the railway at Norsenga timber terminal The old Norsenga bridge had a restriction of max 50 tons total weight, and this will now be increased to 60 tons with the new bridge. New requirements for headroom over the railway means that the road must be raised so that the height of the new Norsenga bridge is adapted. The new Norsenga bridge is a wooden truss bridge with a wooden cover, total 94.5 m long, divided between three spans and founded on pointed concrete piles. The bridge will have 2 lanes and a foot and cycle path. — The new Vingersnoret bridge is a deck bridge in reinforced conrete, total length 33 m, founded on friction piles. The bridge will have 2 lanes with resistant kerbstones against the foot and cycle lane.

Bru 12-2220 Bømla Bridge and Bru no. 12-2222 Stord Bridge Design of dehumidification of carrying cable

Statens vegvesen Region vest | Published June 4, 2016
Winner
COWI A/S
cpvs
71318000, 71321000, 71334000

Hanging bridges on Triangle Link (Stord Bridge and Bømla Bridge) were completed in 2000/2001 and are suspension bridges made with luftspunnede parallel wire cables. The cables were applied to a zinc-containing wrap pasta, wrapped with wire and applied to a painting.

It is now planned to install avfuktingsanlegg for suspension cables for suspension bridges.

This includes dehumidification of cables, splay and tower houses. Scope of work includes complete planning and engineering work for these avfuktingsanleggene.

Bru 12-2220 Bømla Bridge and Bru number. 12-2222 Stord Bridge Design of dehumidification of carrying cable

Statens vegvesen Region vest | Published January 20, 2016  -  Deadline March 14, 2016
cpvs
71318000, 71321000, 71334000

Hanging bridges at Triangle Link (Stord Bridge and Bømla Bridge) was completed in 2000/2001 and are suspension bridges made with luftspunnede parallel wire cables. The cables were applied to a zinc-containing wrap pasta, wound with wire and inflicted a paint.

It is now planned to install avfuktingsanlegg for suspension cables for suspension bridges.

This includes dehumidification of cables, splay and tower houses. The assignment includes delivery of complete planning and engineering work for these avfuktingsanleggene.

Framework agreement on wind tunnel experiment

Statens Vegvesen [The Norwegian Public Roads Administration] | Published November 25, 2016  -  Deadline January 11, 2017
cpvs
71900000, 71335000, 71600000, 71620000, 71632000, 73111000, 73220000, 73430000

The Norwegian Public Roads Administration (SVV) has been tasked with investigating technical solutions to replace all ferry services on E39 with fixed connections. Altogether there are eight ferry services along the route, and five of these fjords are too broad and deep for traditional bridge and tunnel technology to be used. The fjords concerned are Bjørnafjorden, Sulafjorden, Sognefjorden, Halsafjorden and Vartdalsfjorden, and it is ‘Ferry Free E39 sub-project Fjord Crossing’ that has the task of developing concepts for safe and effective crossing of these fjords. The concepts that have been investigated so far fall primarily into three categories: Pontoon bridge, hereunder floating bridge with tension leg anchored towers (TLP type), side anchored floating bridge and floating bridge with only end-anchoring. — Suspension bridge with one or more spans, including suspension bridge on floating foundations. — Submerged floating tunnel, hereunder tension leg anchored or pontoon stabilised. The concepts have different challenges, but commonly they are all very long, slim structures, with significant dynamic stress from wind and waves. The dimensions will vary from fjord to fjord, and between concepts, but the typical bridge length is between 3 000 m and 5 000 m. With the exception of the tunnel bridge, evaluation of wind and wind power is an extremely important part of the design work. It is therefore necessary to carry out experiments in a wind tunnel.

Framework agreements with be signed with three tenderers in each sub-contract.

Entreprise Worker: Terminal Jektevik - Puddefjord Bridge

BIR NETT AS | Published October 6, 2015  -  Deadline November 16, 2015
cpvs
45000000, 45112100

Entreprises main purpose is to develop the boss online with pipe route from BIR Nett its terminal in Jektevik to Puddefjord Bridge, including related installations bossnedkast and manholes. Bergen Municipality Water and Sewerage Authority shall renew parts of the pipework.

Main Inspection of bridges in Østfold, Akershus and Oslo 2015-2020.

Statens vegvesen Region øst (The Norwegian Public Roads Administration, Region East) | Published September 29, 2015
Winner
Dr. Ing. A. Aas-Jakobsen AS
cpvs
71631450, 71000000, 71300000

— Main inspection of bridge elements over water and reporting in BRUTUS for approx. 300 bridges per annum in Østfold, Akershus and Oslo in 2015-2020. The inspections do not include bascule bridges, stay cable bridges or suspension bridges. There will be no or limited supporting walls in this contract. — Main inspection of foundations/erosion protection under water and reporting in BRUTUS for approx. 115 bridges in Østfold, Akershus and Oslo in 2015-2020.

Main Inspection of bridges in Østfold, Akershus and Oslo 2015-2020.

Statens vegvesen Region Øst (the Norwegian Public Roads Administration) | Published June 20, 2015  -  Deadline August 5, 2015
cpvs
71631450, 71000000, 71300000

— Main inspection of bridge elements over water and reporting in BRUTUS for approx. 300 bridges per annum in Østfold, Akershus and Oslo in 2015-2020. The inspections do not include bascule bridges, stay cable bridges or suspension bridges. There will be no or limited supporting walls in this contract. — Main inspection of foundations/erosion protection under water and reporting in BRUTUS for approx. 115 bridges in Østfold, Akershus and Oslo in 2015-2020.

New g / bicycle bridge over Glomma

Sarpsborg kommune, kommunalteknikk | Published May 20, 2014  -  Deadline June 24, 2014
cpvs
45221113, 45000000, 45220000, 45221000, 45221100, 45221110, 45221230, 45223821

Sarpsborg municipality will build a 155 meter long bridge for pedestrian and bicycle traffic over Glomma between Opsund and Hafslundsøy. The bridge must be carried out as a spennbåndsbru and spans 125 m free of Glomma with in situ abutments. It will be built by 37stk prefabricated concrete with 19stk different geometries. The transition between the element and abutments should plasstøpes a length of 7 meters on both sides. The items should be hung on cables stretched between abutments. Country vessels shall be anchored in rock with mountain anchors. In addition, it should be hung 2pcs water mains and 2 x kabeltrekkerør under the bridge that connects the existing VA-trenches on both sides of Glomma. Existing VA route on Opsund page must be on a length of about 100 meters apart because of the new abutments.
Categories
  Norway - Show all countries
Leikanger (140)Arendal (126)Molde (105)Lillehammer (102)Oslo (76)Tilbud eller forespørsel om å delta sendes (65)Bodø (29)Oslo (29)Trondheim (26)Gardermoen (16)Molde (15)Bergen (12)Narvik (12)Vadsø (12)Larvik (11)Sandvika (10)Arendal (9)Sarpsborg (8)Tromsø (8)Gardermoen (7)Odda (7)Alta (5)Fredrikstad (5)Gol (5)Kongsvinger (5)Kristiansand (5)Lillehammer (5)Mo i rana (5)Ringebu (5)Bergen (4)Bardu (4)Drammen (4)Florø (4)Gjøvik (4)Hamar (4)Lillestrøm (4)Skien (4)Sortland (4)Stavanger (4)Tønsberg (4)Brumunddal (3)Eidsvoll (3)Harstad (3)Leikanger (3)Lørenskog (3)Stavanger (3)Steinkjer (3)Støren (3)Tana (3)Ålesund (3)Ålgård (3)Aremark (2)Aurland (2)Bodø (2)Blaker (2)Bruvedlikehold øvre telemark dale bru o/kanal (2)Burfjord (2)Engerdal (2)Eivindvik (2)Finnsnes (2)Geilo (2)Harstad (2)Hattfjelldal (2)Jessheim (2)Kinsarvik (2)Kolbotn (2)Kristiansand s (2)Levanger (2)Lindås (2)Melhus (2)Moss (2)Namsskogan (2)Nesttun (2)Noresund (2)Notodden (2)Otta (2)Rådal (2)Sortland (2)Steinkjer (2)Sandeid (2)Seljord (2)Sunndalsøra (2)Svelgen (2)Trofors (2)Varhaug (2)Vinstra (2)Ål (2)7261 (1)9037 (1)Asker (1)Bjugn (1)Bru nr. 12-3290 gangbru nygårdstangen (1)Bruvedlikehold skar bru, hagabrua og babrua (1)Bryne (1)Bø i telemark (1)Dale (1)Dalenveien bru (1)Drangedal (1)E18 varoddbrua (1)