Public tenders for construction in Varna Bulgaria

Find all Construction tenders in the world.
Finding business opportunities has never been easier.

Results for construction. Make a new search!

Maintenance and after warranty repair of construction machinery with brand New Hоlland, Fiat-Cobelko and Fiat-Hitachi, production of NEW HOLLAND CONSTRUCTION MACHINERY and owned by Varna and Varna

Водоснабдяване и канализация - Варна ООД | Published December 13, 2017  -  Deadline December 14, 2017
cpvs
50114000

When performing the order, technical maintenance and post-warranty repair of construction equipment (excavators - chain and wheel loaders, combined excavator-loaders) with New Hоlland, Fiat-Cobelko and Fiat-Hitachi, NEW HOLLAND CONSTRUCTION MACHINERY of Varna and Varna. The activities, subject of this order, will be carried out at the base of AA and SM division at Water Supply and Sewerage - Varna Ltd.

Construction work

Община Варна | Published October 11, 2017
Winner
„Балкански“ ООД
cpvs
45000000

When executing the contract, the execution of the construction works in connection with the realization of the National Energy Efficiency Program of Multifamily Residential Buildings on the territory of the Municipality of Varna shall be carried out according to Technical Specification according to an approved technical design.

1. Implementation of the construction works according to the investment project, the prescriptions and the orders in the Order book, incl. the cost of the construction and assembly works.

2. Execution of Unforeseen Works, which are types and / or quantities of works that are not included in the investment project and the Quantitative Value Account but whose performance has been proved necessary for the complete and qualitative performance of the Construction;

3. Delivery and installation in the construction of the necessary construction products corresponding to the investment project;

4. Production and / or delivery of Construction parts / elements and equipment and their incorporation in the Construction;

5. Notification to the Contracting Authority of the need for additional design;

6. Performing the necessary tests and laboratory tests;

7. Construction of construction papers and preparation of the construction documentation of the Construction;

8. Participation in the procedure for putting the Construction into operation.

Construction work

Община Варна | Published November 22, 2017  -  Deadline December 28, 2017
cpvs
45000000, 71500000, 71300000, 71315000

1. Preparation of investment projects in the "Technical project" phase; 2. Execution of construction and assembly works under Technical project; 3. Delivery and incorporation in construction of construction products; 4. Production and / or delivery of Construction parts / elements and equipment and their incorporation in the Construction; 5. Notification to the Contracting Authority of the need for additional design; 6. Performing the necessary tests and laboratory tests; 7. Construction of construction papers and preparation of the construction documentation of the Construction; 8. Participation in the procedure for putting the In-service into operation; 9. Removal of the deficiencies identified at the delivery of the Construction and its putting into operation; 10. Removal of defects during the warranty periods specified in the contract for award of the contract in accordance with the tender; 11. Performing Authorized Surveillance.

In the execution of the contract, the execution of Engineering - designing and implementation of construction works in connection with the implementation of the National Energy Efficiency Program for multifamily residential buildings in the territory according to the technical passport and the energy efficiency audit report for Lot 1 with total built-up area 5 136,04 m 2 .

In execution of the contract, the execution of Engineering - designing and implementation of construction works in connection with the implementation of the National Energy Efficiency Program for Multifamily Residential Buildings of the Territory according to the Technical Passport and the Energy Efficiency Audit Report for Separate Item No 2 with total built-up area 6 168,80 m 2 .

In execution of the contract, the execution of Engineering - design and execution of construction works in connection with the implementation of the National Energy Efficiency Program for Multifamily Residential Buildings in the Territory according to the Technical Passport and the Energy Efficiency Audit Report for For lot 3 with total built-up area 4 679,10 m

Construction work

ДП „Пристанищна инфраструктура“, Клон ТП Пристанище Варна | Published August 10, 2016  -  Deadline September 19, 2016
cpvs

Construction work

Construction work

Технически Университет -Варна | Published July 5, 2016
cpvs
45000000

Construction work

Construction work

Община Варна | Published April 19, 2016  -  Deadline May 31, 2016
cpvs
45000000

Construction work

Construction work

Медицински университет „Проф. д-р Параскев Стоянов“ — Варна | Published April 1, 2016  -  Deadline May 14, 2016
cpvs
45000000

Construction work

Construction work

Община Варна | Published April 30, 2016  -  Deadline July 4, 2016
cpvs
45000000, 45231300, 45112000, 45233000

Construction work

Construction work

Община Варна | Published April 30, 2016  -  Deadline June 30, 2016
cpvs
45000000, 45100000, 45220000, 45233140, 45232150

Construction work

Construction work

Община Варна | Published April 30, 2016  -  Deadline June 23, 2016
cpvs
45000000, 71315000, 71221000

Construction work

Construction work

ДП „Пристанищна инфраструктура“, Клон ТП Пристанище Варна | Published September 3, 2016  -  Deadline October 7, 2016
cpvs

It is envisaged that the implementation of these types of construction works:

Construction-site supervision services

Община Варна | Published November 28, 2017
Winner
„СС-Консулт“ ЕООД
cpvs
71521000

In the execution of the order, construction supervision should be exercised on 10 / ten / objects included in each of the separate lots.

The specific responsibilities of the Contractor are to:

178 of the TDA. Construction supervision is performed in the obligatory scope according to the requirements of the Territorial Planning Act, the requirements of Ordinance No. 3 of 2003 for drafting of acts and protocols during construction, taking into account the requirements of the Ordinance on the essential requirements for construction works and conformity assessment of construction products and all statutory and secondary legislation in the field of construction in Bulgaria.

178 of the TDA. Construction supervision is performed in the obligatory scope according to the requirements of the Territorial Planning Act, the requirements of Ordinance No. 3 of 2003 for drafting of acts and protocols during construction, taking into account the requirements of the Ordinance on the essential requirements for construction works and conformity assessment of construction products and all statutory and secondary legislation in the field of construction in Bulgaria.

9

178 of the TDA. The construction supervision is performed in the obligatory scope according to the requirements of the TDA, the requirements of Ordinance No. 3 of 2003 for drafting acts and protocols during construction.

178 of the TDA. The construction supervision is carried out in the obligatory scope according to the requirements of the TDA, the requirements of Ordinance No. 3 of 2003 for drafting acts and protocols during construction.

Construction work

Община Варна | Published May 24, 2017  -  Deadline June 29, 2017
cpvs
45000000, 71320000, 71311000, 45211360

The subject of the contract is the selection of a contractor to develop an investment project in a technical design phase and an investment project in a phase of a project, to undertake the construction of the site: "Sea Garden - Rehabilitation of the street network (including alleys and sites, lighting and elements Of street infrastructure). Reconstruction and construction of new playgrounds for sports and play, recreation areas, park furniture and others. Reconstruction irrigation system, vegetation "and to carry out author's supervision during its construction.

It is envisaged to develop an investment project in the phase of a technical design and investment project in the phase of a detailed design, to make the construction for the site: "Sea Garden - Rehabilitation of the street network (including alleys and sites, lighting and elements of the street infrastructure). Reconstruction and construction of new playgrounds for sports and play, recreation areas, park furniture and others. Reconstruction irrigation system, vegetation. "And be supervised during the construction of this site.

In the framework of the subject of the contract, the following should be done: • studies (if necessary) and biphasic design - drawing up of technical and working projects for the issuance of a construction permit for all parts of the investment design in accordance with Ordinance № 4 / 22.04.2004 Y for scope and content of the investment projects, CC, KSS, catalog with materials used / floorings, lighting fixtures, park furniture, vegetation, etc. /; Reconciliation and subtraction of all necessary permits, incl. building permit; Elaboration of detailed work schedules for the execution of the construction activities; Coordination of drawings and the developed project with all control bodies, operational companies, municipal and state institutions in compliance with the regulatory requirements before submitting the projects of the Contracting Authority for assessment of the compliance with the essential requirements for the construction, approval and obtaining the building permit; Execution of construction works and exercise ...

Construction work

Община Варна | Published October 15, 2016  -  Deadline November 17, 2016
cpvs
45000000

The implementation includes the following activities related to the construction of the facility and are provided a consequence or addition:

Construction work

Община Варна | Published April 29, 2017  -  Deadline June 5, 2017
cpvs
45000000, 45233330, 45233252, 71320000, 71311000, 45221211

The subject of the contract is related to the selection of contractors / contractors to develop investment projects in the technical design phase, to carry out construction works and to carry out author's supervision during the construction for 4 separate positions under the project "Integrated urban transport in Varna - second phase" Of the Municipality of Varna under procedure BG16RFOP001-1.002.

It is envisaged that an investment project will be developed during the technical design stage, and that the construction will be carried out for the project "Reconstruction of the street network" Osmi Primorski polk Blvd. in the section from Vasil Levski Blvd. to Hristo Smirnenski Blvd., incl. Major repair of a transport facility (Vinitsa junction), pedestrian subway and events for improvement of the accessible environment "and to be supervised during construction.

Within the scope of the contract, the following should be done: studies / if necessary / design; Preparation of technical projects for the issuance of a construction permit for all parts of the investment design in accordance with Ordinance № 4 / 22.04.2004 on the scope and contents of the investment projects, CC and KSC; Reconciliation and subtraction of all necessary permits, incl. building permit; Elaboration of detailed work schedules for the execution of the construction activities; Coordination of drawings and the developed projects with all control bodies, operating companies, municipal and state institutions in accordance with the regulatory requirements prior to submission of the projects to the contracting authority for the assessment of the conformity of the projects with the essential requirements for the construction, approval and obtaining of the building permit; Execution of construction works and exercising of author's supervision.

It is envisaged that an investment project will be developed during the technical design phase, and that the construction will be carried out for the project "Reconstruction of a street network along the route of Vasil Levski Blvd. in the section of Podvis to 8th Primorski Polk Blvd. Incl. Cycling, running events to improve the accessible environment and repair of automobile ...

Construction-site supervision services

Община Варна | Published November 15, 2017  -  Deadline December 18, 2017
cpvs
71521000, 71520000

The subject of the contract is the selection of contractors to assess the conformity of investment projects and the exercise of construction supervision of three sites assigned to engineering in the implementation of the project "Modernization of the educational infrastructure on the territory of the city of Varna".

The contractor's specific responsibilities are:

9 SPA; and

178 of the TDA. Construction supervision is performed in the obligatory scope according to the requirements of the Territorial Planning Act, the requirements of Ordinance No. 3 of 2003 for drafting of acts and protocols during construction, taking into account the requirements of the Ordinance on the essential requirements for construction works and conformity assessment of construction products and all statutory and secondary legislation in the field of construction in Bulgaria. At least the following activities are carried out:

- exercising continuous construction supervision over the execution of the construction works according to the technical design and the requirements of the normative acts;

- verification of the completed works and workshops by quantities and prices and signing of the protocols for acceptance of the completed works, prepared by the contractor of the engineering contract on the respective lot / former act model № 19 /;

72/2003), before, during the construction and assembly works and after their completion;

- ensuring the observance of the conditions of work safety, in compliance with the Health and Safety at Work Act (OSH) and the ordinances thereto;

- environmental protection control;

- control over the compliance of inputs and products and other similar activities.

The contractor's specific responsibilities are:

9 SPA; and

178 of the TDA. Construction supervision is performed in the obligatory scope according to the requirements of the Territorial Planning Act, the requirements of Ordinance No. 3 of 2003 for drafting of acts and protocols during construction, taking into account the requirements of the Ordinance on the essential requirements for construction works and conformity assessment of construction products and all statutory and secondary legislation in the field of construction in Bulgaria. At least the following activities are carried out:

- exercising continuous construction supervision over the execution of the construction works according to the technical design and the requirements of the normative acts;

- Verification of the completed works and workshops by quantities and prices and signing of the protocols for acceptance of the completed works, prepared by the contractor of the engineering contract on the respective lot / former act model No 19 /;

72/2003), before, during the construction and assembly works and after their completion;

- ensuring the observance of the conditions of work safety, in compliance with the Health and Safety at Work Act (OSH) and the ordinances thereto;

- environmental protection control;

- control over the compliance of inputs and products and other similar activities.

The specific responsibilities of the Contractor are to:

9 SPA; and

178 of the TDA. Construction supervision is performed in the obligatory scope according to the requirements of the Territorial Planning Act, the requirements of Ordinance No. 3 of 2003 for drafting of acts and protocols during construction, taking into account the requirements of the Ordinance on the essential requirements for construction works and conformity assessment of construction products and all statutory and secondary legislation in the field of construction in Bulgaria. At least the following activities are carried out:

- exercising continuous construction supervision over the execution of the construction works according to the technical design and the requirements of the normative acts;

- Verification of completed works and workshops by quantities and prices and signing of protocols for acceptance of the completed construction and assembly works prepared by the contractor of the engineering contract on the respective lot / former act model No 19 /;

72/2003), before, during the construction and assembly works and after their completion;

- ensuring the observance of the conditions of work safety, in compliance with the Health and Safety at Work Act (OSH) and the ordinances thereto;

- environmental protection control;

- control over the compliance of inputs and products and other similar activities.

Construction consultancy services

Община Варна | Published November 24, 2017
Winner
„СС-Консулт“ ЕООД
cpvs
71530000

When executing the order, the following activities should be performed:

- Pre-investment studies;

- Design and / or coordination of a design assignment;

- Conformity assessment of investment projects under the Territorial Planning Act;

- Checking of project bills;

- Participation of the consultant in expert or other councils;

- Exercise of construction supervision, according to Art. 166, para. 1, item 1 of the Territory Arrangement;

- Reporting the progress of construction works and of completed construction works (preparation of a monthly or extraordinary report, checking and approving the monthly reports of the contractor, preparation of minutes of workshops with the participants in the construction, checking and certifying the quantity and values ​​of the performed Construction and assembly works, etc.);

- Preparation of technical passports of new constructions, according to Ordinance No. 5 / 28.12.2006 (Amended, SG No. 102 of 12.12.2014);

- Investigation and elaboration of a technical passport for existing constructions, according to Ordinance No. 5 / 28.12.2006 (Amended ...

Exercise of construction supervision according to TGS, incl. preparation of a final report according to Art. 168, para. 6 of the Territorial Planning Act and examination and preparation of a technical passport of existing construction sites according to Ordinance No. 5 / 28.12.2006 / amended. SG. 102 from 12.12.2014 / - constructions without execution of the site.

Construction-site supervision services

Община Варна | Published April 5, 2017  -  Deadline May 22, 2017
cpvs
71521000, 71520000

The subject of the contract is related to the selection of contractors to exercise construction supervision during construction of five sites in the implementation of the project - "Modernization of educational infrastructure in the territory of the city" and to assess the compliance of investment projects construction supervision of five other object entrusted to the engineering in implementing the same project.

Construction work

Община Варна | Published February 20, 2015
Winner
„Водоснабдяване и канализация — Варна“ ООД, ЕИК: 103002253
cpvs
45000000, 45231300, 45112000, 45233000

When performing the contract to undertake construction of the pipeline, namely deterioration of asphalt and macadam road; ditches, embankments; trench; supply and installation of pipes and fittings; water abstraction; construction of shafts; supply and installation of unsorted sand and crushed stone compaction; loading and removal of earth; delivery and laying of asphalt; testing of water; protective equipment and facilities for road signs and other construction works, according to an approved investment project. The implementation includes the following activities related to the construction site and are provided consequence or addition: 1. Implementation of works under Technical Design, regulations and orders in the order book, including provided with Quantitative - BoQ works; 2. Implementation of unforeseen work (due to unforeseeable circumstances under PPA), which types and / or amounts of work are not included in investment projects and BoQ but whose implementation has proved necessary for the full and quality execution of the work; 3. Supply and use in the construction of necessary and consistent with the investment project construction products; 4. Production and / or delivery of construction parts / components and equipment and their incorporation in the Works; 5. Notification of the Contracting Authority to the need for additional design; 7. Perform the necessary tests and laboratory tests; 8. Preparation of construction documents and preparation of executive documentation of construction; 9. Participation in the introduction of buildings; 10. Removal of defects in transmission construction and commissioning; 11. Removal of manifest defects during the warranty period stipulated in the contract for the procurement in accordance with the offer.

Construction-site supervision services

Община Варна | Published April 22, 2017  -  Deadline May 29, 2017
cpvs
71521000, 71520000

The subject of the contract is related to the selection of contractors to exercise construction supervision during the construction of three sites in the implementation of project - "Integrated urban transport in Varna - second phase" and to assess the compliance of investment projects and exercising construction supervision during construction of five other sites awarded engineering in implementing the same project.

The specific responsibilities of the contractor are performing:

178 of TDA. The construction supervision is carried out in the compulsory coverage as required by the TDA requirements of Regulation № 3 of 2003 on drawing up acts and protocols during construction, taking into account the requirements of the Ordinance on the essential requirements and conformity assessment of construction products and all laws and regulations in the construction sector in Bulgaria. Perform at least the following activities:

- The continuous construction supervision over the implementation of works, according to the technical design and requirements of the regulations;

- verification of completed construction works in volumes and prices and the protocols on acceptance of the completed works, drawn up by the contractor for construction works in the respective lot / former model act № 19 /;

72/2003) before, during construction works and after their completion;

- Ensuring compliance with the conditions for safety, according to the Health and safety (OHS) and its regulations;

- control of the environmental protection;

- control of the conformity of materials and products and other similar activities.

The specific responsibilities of the Contractor are performing:

178 of TDA. The construction supervision is carried out in the compulsory coverage as required by the TDA requirements of Regulation № 3 of 2003 on drawing up acts and protocols during construction, taking into account the requirements of the Ordinance on the essential requirements and conformity assessment of construction products and all laws and regulations in the construction sector in Bulgaria. Perform at least the following activities:

- The continuous construction supervision over the implementation of works, according to the technical design and requirements of the regulations;

- verification of completed construction works in volumes and prices and the protocols on acceptance of the completed works, drawn up by the contractor for construction works in the respective lot / former model act № 19 /;

72/2003) before, during construction works and after their completion;

- Ensuring compliance with the conditions for safety, according to the Health and safety (OHS) and its regulations;

- control of the environmental protection;

- control of the conformity of materials and products and other similar activities.

The specific responsibilities of the Contractor are performing:

9 LSP; and

178 of TDA. The construction supervision is carried out in the compulsory coverage as required by the TDA requirements of Regulation № 3 of 2003 on drawing up acts and protocols during construction, taking into account the requirements of the Ordinance on the essential requirements and conformity assessment of construction products and all laws and regulations in the construction sector in Bulgaria. Perform at least the following activities:

- The continuous construction supervision over the implementation of works, according to the technical design and requirements of the regulations;

- verification of completed construction works in volumes and prices and the protocols on acceptance of the completed works, drawn up by the contractor for engineering in the respective lot / former model act № 19 /;

72/2003) before, during construction works and after their completion;

- Ensuring compliance with the conditions for safety, according to the Health and safety (OHS) and its regulations;

- control of the environmental protection;

- control of the conformity of materials and products and other similar activities.

The specific responsibilities of the Contractor are performing:

9 LSP; and

178 of TDA. The construction supervision is carried out in the compulsory coverage as required by the TDA requirements of Regulation № 3 of 2003 on drawing up acts and protocols during construction, taking into account the requirements of the Ordinance on the essential requirements and conformity assessment of construction products and all laws and regulations in the construction sector in Bulgaria. Perform at least the following activities:

- The continuous construction supervision over the implementation of works, according to the technical design and