The central complex of the Johannes Gutenberg (Gesamtschule) in Ehringhausen consists of the 3-class gechossigen building with the 1-tailed storey natural science and Polytechnik- / Administration tracts.
625 mThe number of students at the Johannes Gutenberg School is a school year, on average, 1,050 students in up to 45 classes.
The science wing was refurbished in 2012 found.
In 2016, the replacement of heating Central took place.However, the class buildings and Polytechnik- / administrative wing are still fully structurally, home technology, fire protection and energy renovation.
The rehabilitation needs and take place under sensitive consideration of the current school operation in financing and construction phases.
The ground floor is to be adjusted by reorganizing and restructuring of classrooms, workshops, administration and an extension of the assembly hall the revised organizational needs of the school.For the Disabled tapping the installation of an elevator is planned.
This amount for the next phase of construction EUR 3 000 000 gross and includes the following measures:2017 planning and construction planning application Gesamtsanierung
2017/2018 renovation roof areas and cultivation Aula
2018/2019 renovation EC Polytechnic
In the other phases following measures are planned:
2019/2020 EC remediation management
2020/2023 redevelopment ground, 1st, 2nd floor class building
EUR 10 million gross.Due to the previously announced target planning an ENTIRE provision of the power image from the work phases 1-3 will not be necessary.
For budgetary reasons, a gradual, or sections commissioning of services is carried out.
It is envisaged that the school building administration, classroom wing and "Old" to rehabilitate basic way and to toughen the energy and fire safety deficiencies in this course. At the same time accessibility is produce.
The plot of the school complex is located in a central location on the outskirts of Greifenstein, district Beilstein. Of the 4 freestanding buildings only the administrative and classroom wing are connected by a portico. Between the two buildings is a 1-storey toilet wing, which has already undergone interior renovation in the year of 2008. The adjoining gym has been renovated basal 2 years ago and is not part of this action. The grounds of the entire school ensemble has also been rehabilitated.
Architectural services for buildings and interiors for the basic exemplary rehabilitation of administrative, classroom wing and old buildings on the Orange-Nassau-Beilstein school.
The responsible body, the stock plan, as well as the fire protection concept from the year 2010 to the selected candidates in other procedures.
The central building complex of Johannes Gutenberg (Gesamtschule) in Ehringshausen consists of the 3-gechossigen class building with the connected 1-storey natural science and Polytechnik- / administrative districts.
625 mThe number of pupils at the Johannes Gutenberg School has 1050 students in up to 45 classes per school year on average.
The science wing was refurbished in 2012 Design.
In 2016, the renovation of the heating headquarters took place.However, the class of the building and Polytechnik- / administrative offices are still comprising structurally, technically house, fire protection and energy renovation.
The restoration must be carried out under and sensitive consideration of the current school operation in financing and construction phases.
The ground floor is to be adjusted by reorganizing and restructuring of the classrooms, the workshops, the management and cultivation of the Aula the amended organizational needs of the school.For the disabled develop the installation of an elevator is planned.
This amount for the next phase of construction 3 million EUR gross and includes the following measures:2017 planning and construction planning application total renovation;
2017/2018 Restoration roof areas and cultivation hall;
2018/2019 Restoration EC Polytechnic.
In the other phases following measures are planned:
2019/2020 Restoration EC management;
2020/2023 Restoration ground, 1st, 2nd floor class building.
10 million EUR gross.Due to the previously announced target planning an ENTIRE provision of the power of the image of the work phases 1-3 will not be required.
For budgetary reasons, there is a gradual, or sections, commissioning of services.
The cost is according to rough cost estimate:
Cost group 300 - Construction: 1.5 million EUR net;
Cost group 400 - Equipment: 700 000 EUR net.
The planning and execution times of activities are planned for the following period:
Planning performance (LPh 1-7): January 2017-November 2017;
Execution (LPh 8): November 2017 to December 2018.
The responsible construction manager is the general contractor. First, an instruction to the TO with the listed basic services of service phases 1 to 4, the amounts allocated for these Phases special services is provided. From derstufenweisen mandating the AN may not derive any increase of their fees or other claims.The levels are:
Project planning:Power Phase 1 - 4 concerning the special services;
Power Phase 5 (reference details), 6 and 7 with special services;
Performance phase 8 with special services;
Performance stages 9 with special services.
Structural engineering:Performance Phase 1 - 3, with special performances;
Power Phase 4 with special services.
Technical equipment and building physics, all ALG:Power Phase 1 - 4 concerning the special services;
Performance stages 6 and 7 with special services;
Performance phase 8 with special services;
Performance stages 9 with special services.